The critical path in a project network is:______ A. The Shortest path through the network. B. Longest path through the network. C. Network path with the most difficult activities. D. Network path using the most resources.

Answers

Answer 1

Answer:

B

Explanation:

Answer 2

The critical path in a project network is the longest path through the network. The option is B.

What is a project network?

A project network is the diagram that shows the activities and sequences through which the project's various tasks must be completed.

The critical path is part of the project network that has the longest duration which directly impacts the planned project completion date, causing it to take longer to finish the project.

Therefore, the critical path in a project network is the longest path through the network.

Learn more about network here:

https://brainly.com/question/26199042

#SPJ2


Related Questions

For vulnerable road users, the areas where roadways transition from one environment to another are...
A. the safest areas.
B. the most clearly marked areas.
C. the most dangerous areas.

Answers

The answer will be C- the most dangerous areas !!!

For vulnerable road users, the areas where roadways transition from one environment to another are the most dangerous areas. Thus the correct answer is C.

What is the environment?

An environment is refers to surroundings in which all the living and nonliving objects exist to survive life. This includes humans, animals, plants, and other resources.

the areas where roadways transition from one environment to another are the most dangerous areas because here drivers first recognize an approaching change in the nature of the roadway and then reduce their speed as appropriate.

Therefore, option C is appropriate.

Learn more about the environment, here:

brainly.com/question/518189?

#SPJ2

If you know the audience for your website is diverse, what should you do? A. Avoid creating a list of frequently asked questions (FAQs). B. Use a high-tech, complex page design to impress site visitors. C. Provide more than one way to find specific content. D. Incorporate graphics of sports and use sports-related metaphors.

Answers

Answer:

C. Provide more than one way to find specific content.

Explanation:

The website should be made in an innovative and in an attractive way so that the audience, customers, the general public could see your products easily and reach you out in an easy manner.

As you know that your audience for a website is diverse that for that you should need to provide them one more way to determine the specific content as it is easy for them to understand and easily they can access to their website

Hence, the correct option is C.

Make a simple numeric calculator. It should prompt the user for three numbers. Then add the numbers together and divide by 2. Display the result. Your program must support numbers with decimals and not just integers. If the result is more than 6, display Your result is more that 6! 4.

Answers

Answer:

No programming language stated; I'll answer this question using Python.

(Please note that -> at the last line means indentation)

The program is as follows:

num1 = float(input("Number 1: "))

num2 = float(input("Number 2: "))

num3 = float(input("Number 3: "))

result = (num1 + num2 + num3)/2

print("Result: ",result)

if result > 6:

->print("Your result is more than 6!")

Explanation:

The first three lines prompt the user for input of 3 numbers (the number could be decimal, whole numbers, positive or negative numbers)

num1 = float(input("Number 1: "))

num2 = float(input("Number 2: "))

num3 = float(input("Number 3: "))

The next line sums up user input and divides the sum by 2

result = (num1 + num2 + num3)/2

The next line prints the calculated result in the previous line

print("Result: ",result)

The next line determines if the calculated result is more than 6; if yes, the associated print statement is executed

if result > 6:

->print("Your result is more than 6!")

Once again, please note that -> at the last line means indentation

Two stations running TCP/IP are engaged in transferring a file. This file is 1000MB long, the payload size is 100 bytes, and the negotiated window size is 1000 bytes. The sender receives an ACK 1200 from the receiver.

Requried:
a. Which bytes will be sent next?
b. What is the last byte number that can be sent without an ACK being sent by the receiver?

Answers

Answer:

a. 2100

b. 2199

Explanation:

GIven that:

The file size = 1000 MB

The  payload size is  = 100 bytes

The negotiated window size is = 1000 bytes.

This implies that the sliding window can accommodate maximum number of 10 packets

The sender receives an ACK 1200 from the receiver.

Total byte of the file is :

1000 MB = 1024000000 bytes

a.

Sender receives an ACK 1200 from the receiver but still two packets are still unacknowledged

=1200 + 9 * 100

= 1200 +  900

= 2100

b. What is the last byte number that can be sent without an ACK being sent by the receiver?

b. Usually byte number starts from zero, in the first packet, the last byte will be 99 because it is in 1000th place.

Thus; the last byte number send is :

= 1200 + 10 *100 -1

= 1200 + 1000-1

= 1200 + 999

= 2199

print_pattern() prints 5 characters. Call print_pattern() twice to print 10 characters. Example output: ***** ***** in python

Answers

Answer:

def print_pattern():

print("*****",end=" ")

print_pattern()

print_pattern()

Open the Undergrad Debt data in the Excel file. Nationally, on average, a college student last year graduated with $27,200 in debt with a historical standard deviation of $5,000. The file gives sample date from Arkansas.
Does Arkansas students have higher debt than the national average at alpha equal to 10?

Answers

Answer:

Arkansas students have higher debt than the national average, $27,200.

Explanation:

The provided data is:

S = {24040, 19153, 26762, 31923, 31533, 34207, 14623, 24370, 31016}

In this case we need to test whether Arkansas students have higher debt than the national average at alpha equal to 0.10.

The hypothesis can be defined as follows:

H₀: Arkansas students does not have higher debt than the national average, i.e. μ ≤ $27,200.

Hₐ: Arkansas students have higher debt than the national average, i.e. μ > $27,200.

Compute the sample mean:

[tex]\bar x=\frac{1}{n}\sum X=\frac{1}{10}\times 213537=21353.70[/tex]

As the population standard deviation is provided, we will use a z-test for single mean.

Compute the test statistic value as follows:

[tex]z=\frac{\bar x-\mu}{\sigma/\sqrt{n}}=\frac{21353.70-27200}{5000/\sqrt{10}}=-3.70[/tex]

The test statistic value is -3.70.

Decision rule:

If the p-value of the test is less than the significance level then the null hypothesis will be rejected.

Compute the p-value for the test as follows:

 [tex]p-value=P(Z>-3.70)=P(Z<-3.70)=0.00011[/tex]

*Use a z-table for the probability.

The p-value of the test is 0.00011.

p-value = 0.00011 < α = 0.10

The null hypothesis will be rejected.

Thus, it can be concluded that Arkansas students have higher debt than the national average, $27,200.

The list of lists below is meant to represent the money raised by a charity over multiple days. The inner lists represent each donation, and the outer list represents each day. Use a for loop to calculate the sum of all the numbers in this list of list of numbers, to print the total amount of money raised.
code given:hourly_donations_per_day = [[44, 33, 56, 27, 33, 25],[12, 15, 22, 19, 21],[36, 34, 32, 37, 28, 11, 35],[20, 19, 29],[22, 27, 21, 15, 26, 15]]

Answers

Answer:

Following are the code to this question:

hourly_donations_per_day = [ #declaring list of lists and assign values

[44, 33, 56, 27, 33, 25],

[12, 15, 22, 19, 21],

[36, 34, 32, 37, 28, 11, 35],

[20, 19, 29],

[22, 27, 21, 15, 26, 15]

]

total_amount_of_money_raised = 0#defining a variable and assign a values 0

for i in hourly_donations_per_day:#defining loop to count values donation  

       if isinstance(i,list): #using if block to add donation values

               for j in i:#defining loop for add list values

                   total_amount_of_money_raised += j #add all values in total_amount_of_money_raised variable

print(total_amount_of_money_raised) #print value

Output:

714

Explanation:

In the above code, a list of the list is declared in which, it assigns the multiple values, in the inner lists it represents donation value and in the outer list it represents the day. In the next step, a variable "total_amount_of_money_raised" is declared that assigns a value 0, in the next step, multiple for loop is declared which is used to add list donation value and at the last print, the method is used to print its value.    

Write the definition of the function displaySubMenu that displays the following menu; this function doesn't collect the user's input; only display the following menu:
[S]top – Press 'S' to stop.

Answers

Answer:

Using Python:

def displaySubMenu():

   print("[S]top – Press ‘S’ to stop.")

Using C++ programming language:

void displaySubMenu(){

cout<<"[S]top – Press ‘S’ to stop.";}

Explanation:

The function displaySubMenu() has a print statement that prints the following message when this function is called:

[S]top – Press 'S' to stop.

You can invoke this function simply by calling this function as:

displaySubMenu()

The function doesn't take any input from the user and just displays this message on output screen whenever this function is called.

In C++ you can simply call the function using following statement:

void main(){

displaySubMenu(); }

Rijndael, AES, CCMP are same as well as different. They are same in terms of how encryption is done and different in terms of whether each one is a protocol, algorithm or a standard.CCMP is both, a protocol and a standard, Rijndael is:_________ a) standard only b) an algorithm c) a communications protocol. d) patented by US Government

Answers

Answer:

Option (b) is the correct answer to this question.

Explanation:

AES is based on Rijndael Algorithm.

The Rijndael algorithm enables a choice of block sizes and key sizes. The choices are for each of 128, 192, or 256 bits. Once NIST implemented Rijndael for AES, it only specified one block size,128 bits, but maintained three major lengths of selection. IEEE 802.11I go a step and further limits when both the main size and length of the block for 128 bits. It simplifies deployment and relieves users during development from having to make yet again another decision.

Other options are incorrect because they are not related to the given scenario.

A network security analyst received an alert about a potential malware threat on a user’s computer. What can the analyst review to get detailed information about this compromise? Check all that apply

Answers

Complete Question:

A network security analyst received an alert about a potential malware threat on a user’s computer. What can the analyst review to get detailed information about this compromise? Check all that apply.

A. Logs.

B. Full Disk Encryption (FDE).

C. Binary whitelisting software.

D. Security Information and Event Management (SIEM) system.

Answer:

A. Logs.

D. Security Information and Event Management (SIEM) system.

Explanation:

If a network security analyst received an alert about a potential malware threat on a user’s computer. In order to get a detailed information about this compromise, the analyst should review both the logs and Security Information and Event Management (SIEM) system.

In Computer science, logs can be defined as records of events triggered by a user, operating system and other software applications running on a computer. Log files are used to gather information stored on a computer such as user activities, system performance and software program.

Security Information and Event Management (SIEM) system is the process of gathering and integration of all the logs generated by a computer from various software application, service, process, or security tool.

These logs collected through the SIEM are shown in a format that is readable by the security analyst and this help in real-time detection of threats.

Hence, logs and SIEM systems are important tools for network security analyst for detection of threats in real-time and event management functions.

Internally, a bin heap is typically implemented as a BST that has the additional ordering property that the minimum value is at the root (or the maximum value is at the root, if we chose to make the bin heap to be a max heap).
a) True
b) False

Answers

Answer:

True is the correct answer to the given question .

Explanation:

Heap is the complete binary tree that meets the property of organizing the heap There are two types heap max heap and min heap .The value in the heap of every node is greater than or equal to its parent 's value or less then equal to the  parent with there dimension of the minimum value or the maximum value just at the root.

So the binary heap is configured as a Binary Search Tree with the external organizing attribute that perhaps the mean price is in the root with maximum value .

Therefore the given statement is true .

A Solutions Architect needs to build a resilient data warehouse using Amazon Redshift. The Architect needs to rebuild the Redshift cluster in another region. Which approach can the Architect take to address this requirement

Answers

Answer:

Explanation:

An Amazon Redshift data warehouse refers to a collection of computing resources that are known as nodes. These nodes are organized into a group called a cluster. In order to correctly replicate/rebuild this cluster in another region, the Architect needs to modify the Redshift cluster to take snapshots of the Amazon EBS volumes each day, sharing those snapshots with the other region. These snapshots will provide accurate and up-to-date information allowing for a correct rebuild of the Redshift cluster.


How many searches should you complete when looking up information using online references?

Answers

As many as it takes of course ;)

Answer:

c

Explanation:

Complete the method, print Multiples(), that takes in a positive integer n, and another positive integer, max. Print out all the multiples of n that are less than or equal to max. Print each multiple on a separate line. For example, if the method is called with n

Answers

Answer:

public static void printMultiples(int n, int max){

    for (int i=1; i<=max; i++){

        if(i%n == 0)

            System.out.println(i);

    }

}

Explanation:

Create a method called printMultiples that takes two parameters n and max

Inside the method, create a for loop that iterates from 1 to max. If i, a number between 1 and max, % n is equal to 0, that means the number is a multiple of n, print the number.

Write an expression using membership operators that prints "Special number" if special_num is one of the special numbers stored in the list special_list

Answers

Answer:

In python, the statement can be written as:

if(special_num in special_list): print("Special Number")

Explanation:

We need to create a list with the name 'special_list' with some values and then check whether special_num is in the list or not using the membership operator.

Membership operator in python: in

Let us do it step by step in python:

special_list = ['1', '2', '3','4']      #A list with the values 1, 2, 3 and 4

special_num = input("Enter the number to be checked as special \t")

#Taking the input from the user in the variable special_num.

if(special_num in special_list): print("Special Number")

#Using the membership operator in to check whether it exists in the list or not.

Please refer to the image attached for the execution of above program.

So, the answer is:

In python, the statement can be written as:

if(special_num in special_list): print("Special Number")

If your computer freezes on a regular basis and you checked your hard drive and you have insufficient space you've not installed any software that could cause disruption you have recently added more around so you realize that you have enough memory and that isn't causing a problem what could you do to check next? A) Ensure that the computer is disconnected from the internet by removing any Ethernet cables. B) Use scandisk to ensure that the hard drive is not developing errors or bad sectors. C) Replace the CPU and RAM right away. D) Install additional fans to cool the motherboard.

Answers

Answer:

d

Explanation:

If your computer freezes on a regular basis, and you have enough memory and that isn't causing a problem. You should install additional fans to cool the motherboard. The correct option is D.

What is computer freezing?

Computer freezing means the computer is not running smoothly. It is causing concerns in opening any application or running software. It is also called computer hanging. The freezing can occur due to the heating of the motherboard. The addition of the fans would be good.

Freezing on the computer happens when the memories of the computer are full, or any virus has been installed on the computer. Hanging or freezing of computers can be avoided by emptying some data or installing an antivirus.

Thus, the correct option is D. Install additional fans to cool the motherboard.

To learn more about computer freezing, refer to the link:

https://brainly.com/question/15085423

#SPJ2

In cell B13, create a formula using the VLOOKUP function that looks up the value from cell A11 in the range A5:B7, returns the value in column 2, and specifies an exact match.

Answers

Answer:

VLOOKUP(A11,A5:B7,2,0)  is the correct answer to this question.

Explanation:

The VLOOKUP method contains a vertical lookup by scouring for worth in a table's first section and trying to return the significance in the throughout the situation within the same row. The VLOOKUP excel is a built-in function classified as a Lookup / see as.

According to the question:-

The formulation needed to enter is = VLOOKUP(A11, A5: B7,2,0)

The first "A11" here is the cell from which value is retrieved

The second "A5: B7" input is the range for the table where you need to lookup. 2 Is the number of the column from which the value is taken and 0 indicates the exact math

The VLOOKUP function is used to look up a value in a particular column.

The VLOOKUP formula to enter in cell B13 is: VLOOKUP(A11,A5:B7,2,0)

The syntax of a VLOOKUP function is:

VLOOKUP(lookup_value, cell_range, column_index, [return_value])

Where:

lookup_value represents the value to look upcell_range represents the cells to checkcolumn_index represents the column index[return_value] is an optional entry, and it represents the value that will be returned by the look up function.

From the question, we have:

lookup_value = cell A11cell_range = cell A5 to B7column_index = 2[return_value] = 0

So, the VLOOKUP function would be: VLOOKUP(A11,A5:B7,2,0)

Read more about VLOOKUP function at:

https://brainly.com/question/19372969

What are entity-relationship diagrams and how are they used? What symbol is used for a relationship? What is an associative entity? Provide an example.

Answers

Answer:

The definition including its given problem is outlined in the following segment on the clarification.

Explanation:

Entity-relationship (ER) diagram describes how mechanical stored procedures are constructed and demonstrate the overarching representation of the situation. It also describes the connections between some of the entities of the framework and even the comparison with standard measurements.For something like an individual relationship structure, the normal representation of connections seems to be a diamond. Associative institutions have several to many partnerships to communicate with. It's indeed the verb throughout a diamond-shaped form that holds two organizations around each other. This verb is in fact an entity on its own, therefore it must be termed an associative entity.An illustration of such might be if a participant were to register for a class. Multiple individuals will be registered for several courses, and there have been many to several relationships; thus, the associative object will indeed register.

Which among the following enhances WS-Security to facilitate a mechanism for issuing, renewing, and validating security tokens?

a. WS-Trust
b. WS-SecureConversion
c. WS-SecurityPolicy
d. All of the mentioned

Answers

Answer:

a. WS-Trust

Explanation:

WS-Trust can be defined as a WS-specification as well as OASIS standard that help to provides extensions to WS-Security, in order to facilitate a mechanism for issuing, renewing, as well as validating of security tokens which is why the aim and objectives of WS-Trust is to help and enable applications to construct trusted SOAP message exchanges.

Nevertheless WS-Trust enables the issuance as well as the dissemination of credentials within several and various trust domains.

A web service using the WS-Trust can be used for implementing the standards that encode the WS security to facilitate the mechanisms for issuing and reviewing the security tokens.

Hence e the option A is correct. The  WS security token service is a service based on the mechanisms of the key exchange.

Learn more about the following enhances WS-Security to facilitate.

brainly.com/question/13171394.

Those with good motor skills are often described as having ...
A. good coordination.
B. poor coordination.
C. athletic coordination,

Answers

The answer is B. Poor coordination

In the above case, those with good motor skills are often described as having good coordination.

What is good coordination?

A coordination skill is known to bee the ability of a person to look at many moving pieces and derive a plan for all the pieces to be put  together.

Therefore, In the above case, those with good motor skills are often described as having good coordination.

Learn more about good coordination from

https://brainly.com/question/1476231

#SPJ9

If you have taken any drugs, it's not safe to drive.
A. True
B. False

Answers

Answer:

True

Explanation:

It is risky to drive while you are on drugs!

The blank function returns to the first character or characters in a text string based on the number of characters specified??? A. PROPER B. MID C. LEN D. LEFT

Answers

Answer: D.) LEFT

Explanation: LEFT is an excel function allows users to extract a specified number of characters starting from the left. The syntax goes thus :

=LEFT(text, [num_chars])

text: the original string in which characters are to be extracted.

num_chars : takes an integer, stating the number of characters to extract.

The proper function is also an excel function which sets the first character in each word to uppercase. The mid function is also used in text extraction starting from any position in the original string based on what is specified.

The LEN function is used to get the number or length of characters in a string.

all HTML tags are case sensitive, case insensitive and have to be written in capitals only​

Answers

Answer:

Html tags are not case sensitive

It's in JavaScript that the tags are case sensitive

James has a USB flash drive that he has used at work. The drive needs to be thrown away, but James wants to make sure that the data is no longer on the drive before he throws it away. What can James use to wipe the data clean?

a. Zero-fill utility
b. Format the drive
c. ATA Secure Erase
d. Smash the USB drive

Answers

Answer:

C. ATA Secure Erase

D. Smash the USB drive

Explanation:

Zero fill utility is a specialized way of formatting a storage device particularly secondary storage such as hard disk, flash drive e.t.c. In this process, the disk contents are overwritten with zeros. Once this has been done, undoing is essentially hard but possible. In most cases, this might just mean that the data content is corrupt and as such might still be recovered, maybe not in its pure entirety.

Formatting the drive on another hand does not essentially mean cleaning the drive and wiping off data. It just means that operating systems cannot see those data contents anymore. They are still present in the drive and can be recovered.

ATA Secure Erase is actually a way of completely and permanently erasing the content in a drive. Once the function has been done, undoing is not possible. Both the data content and even the data management table will be completely gone.

Smashing the USB drive is the surest way of cleaning data as that will permanently destroy the working components of the drive such as the memory chip. And once that happens then there's no drive let alone its contents.

php Exercise 3: Function Write a function named word_count that accepts a string as its parameter and returns the number of words in the string. A word is a sequence of one or more non-space characters (any character other than ' '). For example, the call of word_count("hello, how are you?") should return 4. Constraints: • Do not use any data structures such as arrays to help you solve this problem. • Do not use the String function explode on this problem. • But you can declare as many simple variables like Integer, String, etc. as you like. Keep it simple.

Answers

Answer:

<?php  

function word_count($string){   // function that takes a string a parameter and returns the number of words in that string

   $space = 0;   // this variable is used in order to detect space, new line and tab spaces in a string

   $words = 1; // this variable is used to identify word presence in string

   $include = $space;  //used to maintain the state of $words and $space

   $counter = 0;  // this counts the number of words in the string

   $i = 0;  //this moves through each character of the string

   while ($i < strlen($string)){  // iterates through every character of string until the last character of string is reached

       if ($string[$i] == " "||$string[$i] == "\n" || $string[$i] == "\t")  //if the space or new line or tab space is identified in the string

           $include = $space;  //set the state of include as space if the next character is a space newline or a tab space

       else if ($include == $space) {  //if next character is a word and current state i.e. $include holds $space

           $include = $words;   //  then set the state i.e. $include as $words

           ++$counter; } //increments i to move to next character at each iteration

       ++$i;  } //returns the number of words in a string

   return $counter; }

$str = "Hello, how are you ";  //sample string

echo "Words: " . word_count($str);  // calls word_count function to return number of words in str.

?>  

Explanation:

The program has a function word_count that accepts a string as its parameter and returns the number of words in the string. In the function there are three variables $space and $words and $include used as state variables. For instance $space identifies space, new line and tab spaces in the $string so it specifies that a space has occurred. $words identifies words in the $string so it specifies that a word has occurred. $include holds this state information. $i moves through every character of the $string and when a space occurs in the $string then the state $include is set to $space. When a word occurs then state $include is set to $words. $counter variable, which is used to count the number of words is incremented to 1 when previous state is $space and next character is a word character. Every time a word is seen in the string, this variable is incremented to 1 to keep track of number of words in the string. When $i reaches the end of the string then this loop stops and counter returns the number of words in the $string.

Which guideline should an employee use when taking notes for a report

Answers

They should respect what is going on and wittiest down everything they can and get it to be the truth or closet to the truth. Also if they say sow,thing happened and they don't want you to right it would be for the best not to right it

1. He is sincere while making report bcz when he make report by heart it is definitely useful.

He is always remain alert bcz any mistake can influence his ratings or project importance

DOLLAR GENERAL
x
Knowledge Check
Non-employees are allowed in the store before the store opens and after
closing time.
True
False
SUBMIT​

Answers

Answer:

False

Explanation:

Unless authorized by a manager. Only staff members are allowed in the store before and after normal store hours.

Answer:

The correct answer is

False

If you are not an employee you are not allowed in stores before opening hours or after closing time. The only times non-staff are allowed in the store is for purchasing of products during hours of operation.h

Hope this helps!

Write a program BandMatrix.java that takes two integer command-line arguments n and width and prints an n-by-n pattern like the ones below, with a zero (0) for each element whose distance from the main diagonal is strictly more than width, and an asterisk (*) for each entry that is not, and two spaces between each 0 or *.

Answers

Answer:

import java.util.Scanner; //Scanner class to take input from user

public class BandMatrix{ // start of the BandMatrix class

   public static void main(String[] args) {// start of main() function body

   Scanner scanner = new Scanner( System.in );

//creates Scanner class object scanner

              int n = scanner.nextInt(); //reads the value of n from user

                   int width = scanner.nextInt(); //reads input value of width

//the outer and inner loops to form a n by n pattern

   for (int i=0; i<n; i++)    {

       for (int j=0; j<n; j++)        {

           if (j==i || Math.abs(i-j) <= width) {

/*if the value of j become equal to the value of i OR if the difference between i and j is less than or equal to the value of width input by user then asterisks are printed in the pattern otherwise 0 is printed. This simply moves through each element of and calculates its distance from main diagonal */

System.out.print(" * ");   } //displays asterisks when above if condition is true

           else            { //when the above IF condition evaluates to false

 System.out.print(" 0 "); }  }  //displays 0 in pattern when if condition is false    

       System.out.println();    } } }

Explanation:

The program is well explained in the comments mentioned with each statement of the program. The program first takes two integer arguments from user i.e. n and width and uses for loops if (j==i || Math.abs(i-j) <= width) condition to print n-by-n pattern with a zero 0 for each element whose distance from the main diagonal is strictly more than width, and an asterisk * for each entry that is not. I will explain the working of loops.

Suppose n=8 and width=0

The first outer for loop has an i variable that is initialized to 0. This loop executes until the value of i exceeds the value of n. So at first iteration i=0. The loop checks if i<n. Its true because n=8 and i=0 So 8>0. Now the program enters the body of outer loop.

There is an inner loop which has a j variable that is initialized to 0. This loop executes until the value of j exceeds the value of n. So at first iteration j=0. The loop checks if j<n. Its true because n=8 and j=0 So 8>0. Now the program enters the body of inner loop.

There is an if statement inside the body of inner loop. It checks each entry whose distance from the main diagonal is strictly less than or equal width and prints asterisks * when the statement evaluates to true otherwise prints a 0. Lets see how it works.  

i=0 j=0 So j==i is True. If we check the second part of this if statement then

i - j = 0 - 0 = 0. Math.abs() method is used to return the absolute value of this subtraction in case the result comes out to be a negative number. So the result is 0. As the value of width is 0 so this part is true because i-j=0 and width is also 0. So one asterisk is printed when this condition evaluates to true.

This way the loops keeps executing and printing the asterisks or 0 according to the if statement at each iteration. The program along with its output is attached.

All the protocol layers of the internet (Application, Transport. Network) were originally without any security. TLS is one of the security architectures added later. In the Internet protocol stack. TLS is located:________. 1. right above the application layer 2. right below the application layer 3. right below the transport layer 4. right above the IP layer

Answers

Answer:

2. right below the application layer

Explanation:

TLS (Transport Layer Security) is an improved and more secured version of the SSL (Secure Socket Layer) used as cryptographic protocol for providing authentication and encryption over a network. It is initialized at the transport layer of the IP stack and finalized at the application layer. In other words, it is located between the transport and application layer of the Internet protocol stack. And this is necessary so that data received in the application layer from the transport layer are protected from start to end between these two layers.

Therefore, it is safe to say that the TLS is located right below the application layer.  

write the algorithm, flowchart and BASIC program to calculate the area of the rectangle length 50m and width 30m.​

Answers

Answer:

The Basic Program is as follows:

10 LENGTH = 50

15 WIDTH = 30

20 AREA = WIDTH * LENGTH

25 PRINT AREA

30 END

The Algorithm is as follows:

1. Start

2. Let Length = 50

3. Let Width = 30

4. Compute Area = Length * Width

5. Display Area

6. Stop

See Attachment for flowchart (flowchart is designed using draw io tools)

Explanation:

The flowchart, algorithm and basic program all follow the same sequence and explanation

Using the basic program as a case study;

Line number 10: The program starts by initializing LENGTH to 50

Line number 15: It then initializes WIDTH to 30

Line number 20: The AREA is calculated by LENGTH * WIDTH

Line number 25: The value of AREA is printed afterwards

Line number 30: Lastly, the program stops execution

Other Questions
If a company presently has B+ credit rating, which one of the following will NOT contribute to achieving a higher credit rating? A. A "low" default risk ratio B. Larger retained earnings C. A lower debt to assets ratio D. A higher interest coverage ratio E. A higher default risk ratio -1. - ,- -, , - , , -- (i) - ?(ii) '- ' - ?(iii) Geneticists have discovered the existence of meiotic drive genes, which have alleles that, when present in a heterozygous state, are able to become incorporated into much more than 50 percent of the gametes. As a result, the offspring ratios are not what Mendel would have predicted. Which statement about these meiotic drive genes is true The master budget of Carpenter Company shows that the planned activity level for next year is expected to be 100,000 machine hours. At this level of activity, the following manufacturing overhead costs are expected: Indirect labor $480,000 Machine supplies 120,000 Indirect materials 140,000 Depreciation on factory building 100,000 Total manufacturing overhead $840,000 A flexible budget for a level of activity of 120,000 machine hours would show total manufacturing overhead costs of: Fifteen women can weed a piece of land in 12 days. How many more women will be required to clear the same land in10 days 7x-14=3x+12Solve for x! A foundation was endowed with $15,000,000 in July 2010. In July 2014, $5,000,000 was expended for facilities, and it was decided to provide $250,000 at the end of each year forever to cover operating expenses. The first operating expense is in July 2015, and the first replacement expense in July 2014. If all money earns interest at 5% after the time of endowment, what amount would be available for the capital replacements at the end of every fifth year forever I NEED HELP PLEASE, THANKS! :) What is the axis of symmetry and vertex for the function f(x) = 3(x - 2)2 + 4?x=Vertex: Jennifer and Stella are cooks at a restaurant that serves breakfast. On a particular day, the two of them tracked the number of pancakes they cooked. The number of pancakes that Jennifer cooked is represented by the following function, where x is the number of hours. The number of pancakes that Stella cooked is shown by the graph below. Who cooked more pancakes in 8 hours? 11. A roofer calculates his bid price using the formula P = 1.85s + 4.2f, where s is the area of the roof in square feet and f is the length of the fascia in feet. Find the area of the roof with 190 feet of fascia and a price of $4,148. Round to the nearest square foot Please help i will mark brainliest! How can a government function What is the output of the following function for x = -4?F(x) = 3x^5 + 4x^3 -x +11 All of the following were advantages enjoyed by the British during the American Revolution EXCEPT: A. the ability to recruit German soldiers to fight for them. B. the world's best navy. C. an intimate knowledge of the terrain. D. a professionally trained army. E. the ability to lure slaves to fight for them in exchange for their freedom. What is the x-intercept of y=x^2+6x-8 Find the value.X3+ X2 when x=-2PLEASE HELP!!! ASAP!!! Determine the amount of time for polonium-210 to decay to one fourth its original quantity. The half-life of polonium-210 is 138 days. Explain. Representa la unin inica entre los siguientes tomos: 1) Bromo y Potasio 2) Calcio y Oxgeno 3) Cloro y Magnesio 4) Sodio y Flor 5) Aluminio y Nitrgeno Ayuda por favoor What is the formula of life ace 3 work book 4