Which of the following are input into the "Define Scope"
process?
a) The Scope Statement
b) The WBS
c) Status Reports
d) The project charter

Answers

Answer 1

The correct inputs for the "Define Scope" process are the Scope Statement, the WBS, and the project charter. (Option A, B and D).

What is Define Scope Process?

The "Define Scope" procedure, which is a component of project management, entails precisely defining and recording the project's parameters, deliverables, and goals. It is an important project planning stage that lays the groundwork for all following project operations.

Establishing a shared understanding among stakeholders about what is included and excluded from the project is the main objective of the Define Scope procedure. It aids in preventing scope creep, which is the unchecked expansion of a project's scope over its intended boundaries.

Learn more about Define Scope Process here: https://brainly.com/question/30301515

#SPJ4