Answer:
see below
Step-by-step explanation:
The difference between start and end times is the duration in each case.
The earliest start time is the latest of the earliest finish times of all predecessor tasks. These are computed working left to right.
The latest finish time is the earliest of the latest start times of all successor tasks. These are computed working right to left.
Where earliest and latest times are the same, the task is on the critical path. (It has no slack time.)
The above computations have been built into the attached spreadsheet. Here, predecessors and successors are handled manually. In appropriate scheduling software, they would be handled automatically by the specification of the task relationships.
If f(x) = x-5 and g(x) = 3x2-1,
what is (fºg)(x)?
Answer:
[tex](f\circ \: g)(x) = {3x}^{2} - 6[/tex]Step-by-step explanation:
f(x) = x - 5
g(x) = 3x² - 1
To find (fºg)(x) substitute g(x) into f(x) that's for every x in f (x) replace it with g (x)
That's
[tex](f\circ \: g)(x) = 3 {x}^{2} -1 - 5 [/tex]We have the final answer as
[tex](f\circ \: g)(x) = {3x}^{2} - 6[/tex]Hope this helps you
HW Score: 10%,
2 of 5 (1 completo)
Score: 0 of 1 pt
Question Help
2.2.23
A delivery person uses a service elevator to bring boxes of books up to an office. The delivery person weighs 190 lb and each box of books weighs 60 lb. The maximum capacity of the elevator is 1140 b. How many boxes of
books can the delivery person bring up at one time?
3, 7, 11, 15, 19, 23, ...
what’s the next number in the pattern then explain how you got the answer
Answer:
27
Step-by-step explanation:
if you add 4 to 3 you get 7 and if you add 4 to 7 you get 11 so keep adding 4 to all the numbers and you will get the next number.
Answer:
The pattern is going by 4 so your next number would be 27
Step-by-step explanation:
Count from 3 to reach 7 then you get 4 same goes for the rest of the numbers so if you count 4 more of 23 you get 27
Hope that answered ur question
Evaluate p/2-5 when p=14
Answer:
[tex] - 4.67[/tex]
Step-by-step explanation:
[tex] \frac{p}{2 - 5} = \frac{14}{2 - 5} = \frac{14}{ - 3} = - 4.67[/tex]
Where can you put parenthese so that the answer is correct 28-24/4•2=25
Answer:
This really is about trial and error
28-24/(4*2)=25
Step-by-step explanation:
If you do this correctly, the numbers you'll get are 28-3 = 25!
Hope this helps!! :)
Answer:
I think this is the answer
How can you plot a point using its (x,y) coordinates?
Answer:
each
Step-by-step explanation:
Please help! I will mark brainliest.
Help please I am confused inverse variation problem
Answer:
y =2
Step-by-step explanation:
Inverse variation is of the form
xy = k
3*6 = k
18 = k
xy = 18
Now when x = 9, find y
9*y = 18
Divide by 9
y = 18/9
y =2
When x =9, y =2
Answer:
y = 2
Step-by-step explanation:
y = 6 ⇔ x= 3
y = ? ⇔ x = 9
y = 6*3/9
y = 2
is -12, -10, -8, and -6 linear, exponential or neither
Answer:
Linear
Step-by-step explanation:
It goes up by 2 each time, so it would be linear.
Tamara earns $15 an hour at her job working 30 hours per week. If her net pay is 72% of her paycheck and she has no other sources of income, what is Tamara’s monthly cash inflow? (Assume there are 4 pays per month )
Answer:
126
Step-by-step explanat
(30)(15) - (72%)
Answer:
$1296
Step-by-step explanation:
paycheck in 1 month: $15/hour * 30 hours/week * 4 weeks/month = $1800/month
net pay = 72% of paycheck in 1 month = 72% of $1800 =
= 0.72 * $1800 = $1296
whats the answer to this
Answer:
Step-by-step explanation:
sweet
12v+10v+14=80 solve the equation
Answer:
v=3
Step-by-step explanation:
4 books for 1$12.00 3 books for $9.00 What is the price per book? What is the constant of proportionality
Answer:
the price per book is $3 the constant of proportionality is 3
Step-by-step explanation:
12 divided by 4 is 3 and 9 divided by 3 is 3 so it means that the price for 1 book is going to be 3 and for every book you buy the original value will be 3.
(-12)^9 negative or positive
A box with no top that has a volume of 1000 cubic inches is to be constructed from a 22 x 30-inch sheet of cardboard by cutting squares of equal size from each corner and folding up the flaps. If one of the dimensions has to be greater than 18 inches, what size square should be cut from each corner?
a. 2.234 in
C. 1.369 in
b. 3.784 in
d. 2.758 in
Answer:
a: 2.234
Step-by-step explanation:
i checked after i took the test. its right, enjoy
The size of the square cut from each corner will be 1.369 inches. The correct option is C.
What is geometry?Geometry is one of the oldest branches of mathematics, along with arithmetic. It is concerned with spatial properties such as figure distance, shape, size, and relative position.
Given that a box with no top that has a volume of 1000 cubic inches is to be constructed from a 22 x 30-inch sheet of cardboard by cutting squares of equal size from each corner and folding up the flaps.
The size of the square cut from each corner will be calculated as,
Volume = L x H x W
1000 = 22 x 30 x H
H = ( 1000 ) / ( 660 )
H = 1.538 or 1.369 inches
Therefore, the size will be 1.369 inches.
To know more about geometry follow
https://brainly.com/question/9325797
#SPJ2
How do i solve 6(2-4y) +4(6y-2)<4(y+4)
[tex]6(2-4y) +4(6y-2)<4(y+4)[/tex] (distribute)
[tex]12-24y+24y-8<4y+16[/tex] (collect like-terms)
[tex]12-8<4y+16\\4<4y+16\\-4y<16-4\\-4y<12\\y>\frac{12}{-4}[/tex] (we flipped the sign because we divided by a negative)
[tex]y>-3[/tex]
What is the solution to this system of equations?
x+y=7
x=y+3
(i’ve never understood ones like this so please help!!)
Answer:
x=5 and y=2
Step-by-step explanation:
[tex]x=y+3\\x=2+3\\x=5[/tex] [tex]x+y=7\\y+3+y=7\\2y+3=7\\2y=7-3\\2y=4\\ \frac{2y}{2}=\frac{4}{2}\\ y=2[/tex]
The solution of the system, x + y = 7, x = y + 3 is x = 5 and y = 2.
What is the equation?Equation: A statement that two variable or integer expressions are equal. In essence, equations are questions, and the motivation for the development of mathematics has been the systematic search for the answers to these questions.
Equations are statements in mathematics that have two algebraic expressions on either side of the equals (=) sign. It shows that the expressions printed on the left and right sides have an equal relationship.
Given:
x + y = 7
x = y + 3
Write both equations as shown below,
x = -y + 7
x = y + 3
Add both equations,
x + x = -y + y + 7 + 3
2x = 10
x = 5,
5 = y + 3
y = 5 - 3
y = 2
To know more about equation:
https://brainly.com/question/12788590
#SPJ2
The effect of the time of day a psychology class is taught on test scores is
being studied in an experiment. The difficulty of test questions has been
identified as an extraneous factor that could also affect test scores. How ca
the difficulty of test questions best be addressed to minimize its effect in th
experiment?
O A. Blocking into groups based on the teacher of the class
O B. Replication of the experiment at different times of the year
O C. Randomization of students in morning and afternoon classes
D. Direct control by requiring every class to take the same test
The correct answer will be option C Randomization of students in morning and afternoon classes.
What is psychology?Psychology is the scientific study of the mind and behavior, according to the American Psychological Association.
The only way to minimize this effect would be through randomization of students in morning and afternoon classes.
Doing so apply the factor of skill from an individual student to either time of day class greatly lessens the overall effect that it has on the results.
This therefore, minimizes the effect it has on the experiment itself, since the same students that have been studying in a certain time of day would be randomized and not have the same environment that they are used to.
To know more about Psychology follow
https://brainly.com/question/12011520
#SPJ2
Answer:
Step-by-step explanation:
Direct control by requiring every class to take the same test
indeed some help me plz
Answer:
3
Step-by-step explanation:
15-2x=3x
or,3x+2x=15
or,5x=15
or,x=15/5
Therefore, x=3.
Ankit makes 74% of the free throws he takes in his basketball league. If he is fouled on a three-point shot and gets three free throws, what is the approximate probability he will make all three shots?
The approximate probability that Ankit will make all three shots is 0.405 or 40.5%.
What is binomial distribution?A probability distribution known as the binomial distribution is used to characterize the number of successes in a certain number of independent trials, where each trial has only one of two potential outcomes (success or failure) and the chance of success is constant across all trials. For determining the likelihood of achieving a certain number of successes in a set number of trials, it is utilised.
Given, Ankit makes 74% of the free throws.
Using binomial distribution we have:
[tex]P(X=k) = (n C k) * p^k * (1-p)^{(n-k)}[/tex]
For k = 3 we have:
[tex]P(X=3) = (3 C 3) * 0.74^3 * (1-0.74)^{(3-3)}\\\\P(X=3) = 0.74^3[/tex]
P(X=3) ≈ 0.405
Hence, the approximate probability that Ankit will make all three shots is 0.405 or 40.5%.
Learn more about binomial distribution here:
https://brainly.com/question/31197941
#SPJ1
What is the square root of 255
Answer:
the square root of 225 is 15.9
Answer:
15.♾
Step-by-step explanation:
*PLEASE ANSWER ASAP* Taylor is playing a board game with two friends. Using a single die, one friend rolled a one, and the other friend rolled a three. Taylor needs to roll a number higher than both friends in order to win the game, and she wants to calculate her probability of winning. What is the probability that Taylor will win the game?
Answer:
D
Step-by-step explanation:
So, one friend rolled a 1 and the other rolled a 3. Taylor needs to roll a number higher than both friends in order to win.
So, the possible numbers Taylor can roll to win are 4, 5, or 6.
Out of the six possible choices, 4, 5, and 6 is takes up 3. Thus, the chances of Taylor winning is:
[tex]3/6=50\%[/tex]
The answer is D.
Miss K wants to get Portillos with 5 of her teacher
friends. She decides to split a pizza and 6 drinks. If the
pizza cost $11.50, and they spend a total of $18.50,
how much does one drink cost?
Show ALL work in this box!
Answer: $1.17 per drink
Step-by-step explanation:
Let x=the cost of one drink
11.5+6x=18.5
subtract 11.5 on both sides
11.5+6x-11.5=18.5-11.5
6x=7
Divide 6 on both sides
6/6 x=7/6
x=7/6
7/6≈$1.17
Hope this helps!! :)
Please let me know if you have any question
Hailey signed up for a streaming music service that costs $14 per month. The service allows Hailey to listen to unlimited music, but if she wants to download songs for offline listening, the service charges $1.50 per song. How much total money would Hailey have to pay in a month in which she downloaded 40 songs? How much would she have to pay if she downloaded ss songs?
Answer:
The total is: 74$
Step-by-step explanation:
1.50$ times 40 equals 60. Then you have to add up the cost you usually get per month which is 14$. 60 plus 14$ = 74$
An expression is a way of writing a statement with more than two variables or numbers with operations such as addition, subtraction, multiplication, and division.
The total money to pay in a month in which she downloaded 40 songs is $74.
What is an expression?An expression is a way of writing a statement with more than two variables or numbers with operations such as addition, subtraction, multiplication, and division.
Example: 2 + 3x + 4y = 7 is an expression.
We have,
Cost per month for streaming music = $14
Cost per song for download = $1.50
Total cost for downloading 40 songs.
= 40 x 1.50
= $60
The total cost for the month.
= Monthly charges + Cost of downloading 40 songs
= $14 + $60
= $74
Thus,
The total money to pay in a month in which she downloaded 40 songs is $74.
Learn more about expressions here:
https://brainly.com/question/3118662
#SPJ2
Henrique began to solve a system of linear equations using the linear combination method. His work is shown below Complete the steps used to solve a system of linear equations by substituting the value of y into one of the original equations to find the value of x. What is the solution to the system?
Complete question is;
Henrique began to solve a system of linear equations using the linear combination method. his work is shown below
1. 3 (4x-7y=28) -> 12x-21y=84
-2 (6x-5y=31) -> -12x 10y =62
2. 12x - 21y = 84
-12x + 10y = -62
-----------------------
-11y = 22
3. y= -2
complete the steps used to solve a system of linear equations by substituting the value of y into one of the original equation s to find the value of x. what is the solution to the system
Answer:
x = 3.5
Step-by-step explanation:
We are given;
1. 3(4x - 7y = 28) -> 12x - 21y = 84
-2(6x - 5y = 31) -> -12x + 10y = 62
2. 12x - 21y = 84
-12x + 10y = -62
-----------------------
-11y = 22
3. y= -2
Since y = - 2, let's put -2 for y into the equation; 12x - 21y = 84
This gives;
12x - 21(-2) = 84
This gives;
12x + 42 = 84
12x = 84 - 42
12x = 42
x = 42/12
x = 3.5
The temperature is at -2 F at 6A.M. During the next three hours, the temperature increases to 15F. What is the temperature at 9A.M. Enter your answer in integer form
Answer:
Temperature at 9 A.M = 13° F
Step-by-step explanation:
Given:
Temperature at 6 A.M = - 2° F
Temperature increases in 3 hours = 15° F
Find:
Temperature at 9 A.M
Computation:
Temperature at 9 A.M = Temperature at 6 A.M + Temperature increases in 3 hours
Temperature at 9 A.M = - 2° F + 15° F
Temperature at 9 A.M = 13° F
What’s the answer to this question?
Answer:
report that dude the answer is:
-7.75
Step-by-step explanation:
(1/2)^2 - 6(2 - 2/3)
First we get rid of the exponent 2 by muliplying the (1/2) two times.
(1/2)×(1/2) = 1/4
Now we have:
1/4 - 6(2 - 2/3)
Now we solve the equation in the other paraenthesis:
(2 - 2/3) = 1 1/3
Now we plug it back in:
1/4 - 6(1 1/3)
Now we mulitply the 6 with the fraction 1 1/3 in the paraenthesis:
6(1 1/3) = 8
Now we plug it back in:
1/4 - 8
Now finally solve this fraction:
-7.75
4a4 − 2b2 + 40 when a = 2 and b = 7.
Answer:
44
Step-by-step explanation:
4(2)4 - 2(7)2 + 40
32 - 28 + 40
44
Answer: 6
Step-by-step explanation:
4a^4-2b^2+40, given a=2 and b=7
4a^4-2b^2+40
=4(2)^4-2(7)^2+40
=4(16)-2(49)+40
=64-98+40
=-34+40
=6
Hope this helps!! :)
Please let me know if you have any question
Write the equation of the line that passes through (1, 5) and (−2, 14) in slope-intercept form. (2 points) y = 3x + 2 y = 3x + 8 y = −3x − 2 y = −3x + 8
Answer:
work shown and pictured
What is the solution set for the inequality?
-6x+9>7x+74
Answer:
Step-by-step explanation:
- 6x + 9 > 7x + 74
Treat them as being equal first.
Subtract 9 from both sides.
- 6x + 9 - 9 > 7x + 74 - 9
- 6x > 7x + 65
Subtract 7x from each side
- 6x - 7x > 7x - 7x + 65
- 13x > 65
Divide each side by -13
- 13x / -13 > 65 / -13
x < -5
So x hust be smaller than -5 meaning -6 works but -4 doesn't.