Answer: 7.0
Step-by-step explanation:
sergio must ride 7.5 miles in 1/4 hour to achieve this target speed so he needs to ride an addititonal 9.8 mile per1/4 hour
Answer:
30 mph
Step-by-step explanation:
since it is 1/4 you would multply 7.5 times 4, which adds up to 30.
Can someone help me? Please i need this done
How do you get from one number to the next using multiplication or division?
From 100 to 106
From 100 to 90
From 90 to 100
From 106 to 100
Answer:
You use decimal values. Like for the first one, multiply 100 by 0.01.
Step-by-step explanation:
The multiplication or division is 10^6/10^4
How to interpret integral multiplication?Suppose that there are two positive integer numbers( numbers like 1,2,3,.. ) as a and b
Then, their multiplication can be interpreted as:
[tex]a \times b = a + a + ... + a \: \text{(b times)}\\\\a \times b = b + b +... + b \: \text{(a times)}[/tex]
For example,
[tex]5 \times 2 = 10 = 2 + 2 + 2 + 2 + 2 \: \text{(Added 2 five times)}\\or\\5 \times 2 = 10 = 5 + 5 \: \text{(Added 5 two times)}[/tex]
Given;
From 100 to 10^6;
100 * 10^4 = 10^6
From 100 to 90;
100/10*9=90
From 90 to 100
90/9*10=100
From 10^6 to 100
10^6/10^4=100
Therefore, by multiplication or division will be 10^6/10^4
Learn more about multiplication here:
https://brainly.com/question/26816519
#SPJ2
3. From the table below, find Prof. Xin expected value of lateness. (5 points) Lateness P(Lateness) On Time 4/5 1 Hour Late 1/10 2 Hours Late 1/20 3 Hours Late 1/20
Answer:
The expected value of lateness [tex]\frac{7}{20}[/tex] hours.
Step-by-step explanation:
The probability distribution of lateness is as follows:
Lateness P (Lateness)
On Time 4/5
1 Hour Late 1/10
2 Hours Late 1/20
3 Hours Late 1/20
The formula of expected value of a random variable is:
[tex]E(X)=\sum x\cdot P(X=x)[/tex]
Compute the expected value of lateness as follows:
[tex]E(X)=\sum x\cdot P(X=x)[/tex]
[tex]=(0\times \frac{4}{5})+(1\times \frac{1}{10})+(2\times \frac{1}{20})+(3\times \frac{1}{20})\\\\=0+\frac{1}{10}+\frac{1}{10}+\frac{3}{20}\\\\=\frac{2+2+3}{20}\\\\=\frac{7}{20}[/tex]
Thus, the expected value of lateness [tex]\frac{7}{20}[/tex] hours.
An expected value is the theoretical mean value of a numerical experiment over many repetitions of the experiment.
Expected value of lateness is [tex]\frac{7}{20}[/tex] hours.
Let us consider, P(x) is represent that probability of lateness and x represent number of hours late.
So, below a table is formed.
x 0 1 2 3
P(x) 4/5 1/10 1/20 1/20
From formula of expected value,
E(x) = ∑ x P(x)
[tex]E(x)=(0*\frac{4}{5} )+(1*\frac{1}{10} )+(2*\frac{1}{20} )+(3*\frac{1}{20} )\\\\E(x)=0+\frac{1}{10}+\frac{1}{10}+\frac{3}{20} \\\\E(x)=\frac{7}{20}[/tex]
So, expected value of lateness is 7/20 hours.
Learn more:
https://brainly.com/question/23286309
2)
Mike went to the doctor and was found to be 20 pounds overweight.
The doctor discovered that Mike ate an average of 2000 calories per
day. He said for Mike to lose weight and meet his goal, the maximum
amount of calories he could eat per day was 1750. How many calories
will Mike be cutting out each week (7 days)?
Answer:
1750 Calories
Step-by-step explanation:
2000-1750=250
250x7=1750
Poooo sieieoleltlrllrlr
Answer:
ol rjlrjlfjcohcoucoycl lj
Answer:
:3
Step-by-step explanation: