In order to avoid long-term dilution, a corporation should determine whether the necessary additional earnings from the issue are realistic relative to their historic
profit margin.
times interest earned.
total asset turnover.
return on assets.

Answers

Answer 1

When a corporation is considering issuing more shares of stock, it is important for them to determine whether the additional earnings that would come from the issue are realistic relative to their historic profit margin.

This is because if the earnings from the new shares are not sufficient to cover the dilution caused by the increased number of shares outstanding, the existing shareholders' ownership percentage and earnings per share will be reduced. One way to assess whether the additional earnings are realistic is to look at the corporation's times interest earned ratio, which measures its ability to meet its interest obligations. If this ratio is low, it may indicate that the corporation is already struggling to generate sufficient earnings to cover its existing financial obligations and may not be able to generate enough additional earnings to cover the dilution caused by the new shares. Similarly, it can be helpful to look at the corporation's total asset turnover and return on assets ratios. These ratios provide insight into the efficiency with which the corporation is using its assets to generate earnings. If these ratios are low, it may indicate that the corporation is not generating enough earnings from its existing assets to justify the issuance of additional shares.
Overall, corporations should carefully consider the potential long-term dilution caused by the issuance of additional shares and ensure that the necessary additional earnings are realistic relative to their historic performance and financial obligations.

To know more about considering visit :-

https://brainly.com/question/28144663

#SPJ11


Related Questions

A company manufactures two wheeler passengers’ helmets. The initial stock on hand is 5000 units. The carrying cost is Rs. 2 per helmet per week and the lead time is two weeks. The ordering cost per order is Rs. 5000. The MPS of the final requirements is shown below. Develop a Material Requirement Plan (MRP I) by using EOQ method and determine the total inventory cost for the same.

Answers

The total inventory cost is Rs. 10, 000. MRP (Material Requirement Planning) is a technique of preparing a product manufacturing schedule, outlining the parts and materials necessary for product production and the timing of that production. It entails estimating how much product is needed, when it is required, and in what quantities.

The manufacturing process must always be ready for orders and be equipped with sufficient raw materials for this reason. The EOQ (Economic Order Quantity) method, on the other hand, is a stock management technique that is used to determine the optimum order quantity for stock items. It is based on the principle that inventory-related costs should be kept to a minimum while stock items are available when required for production and sales.

A Material Requirement Plan (MRP) can be developed by utilizing the EOQ method. Here is how you can determine the total inventory cost for the same:Q = √(2SD/CC)EOQ = √(2SD/CC) = √(2 x 20000 x 5000/2) = √(20000000/2) = √10000000 = 3162 units.Cost of the unit = Rs. 2.Ordering cost = Rs. 5000.Carrying cost = Rs. 2 per unit per week.Lead time = 2 weeks.MPS =3000; 2000; 4000; 3500; 5000; 6000; 4000; 2500Week(1); (2); (3); (4); (5); (6); (7); (8)Product DemandLot Size (Order Quantity)Planned Order ReceiptsPlanned Order ReleasePlanned

To know more about product production visit:

https://brainly.com/question/31859289

#SPJ11

Risk associated with building a hospital in Soweto South
Africa

Answers

Building a hospital in Soweto, South Africa comes with several risks that need to be taken into consideration. One of the primary concerns is the high crime rate in the area, which could pose a threat to the safety of patients and medical staff.

The hospital would need to have adequate security measures in place to prevent theft, vandalism, and violence. Additionally, there is a risk of communicable diseases in Soweto due to poor sanitation and living conditions. Therefore, the hospital would need to implement strict infection control protocols to prevent the spread of diseases. Another risk is the lack of skilled healthcare professionals in the area, which could affect the quality of care provided to patients. Finally, there is a risk of financial loss if the hospital fails to attract enough patients or receive adequate funding. Overall, building a hospital in Soweto requires careful planning and risk management to ensure the safety of patients and staff, as well as the success of the hospital in the long term.

To know more about risks  visit:

https://brainly.com/question/30168545

#SPJ11

5-
state the characteristics of effective controlling
6- differentiate between the operational control
types

Answers

The characteristics of effective controlling include establishing clear objectives, measurable standards, timely feedback, flexibility, and corrective action.

Effective controlling involves setting clear and specific objectives that provide a basis for measuring performance. Measurable standards are essential, as they enable the comparison of actual performance against the established criteria. Timely feedback ensures that deviations from standards are identified promptly, allowing for timely corrective action. Flexibility in controlling allows for adjustments in response to changing circumstances. Finally, effective controlling involves taking corrective action to address deviations and improve future performance. By embodying these characteristics, controlling helps organizations stay on track, achieve their goals, and maintain optimal performance levels.

To know more about effective controlling, visit:

https://brainly.com/question/30551667

#SPJ11

An alliance qualifies as strategic only if it has the potential to affect a firm’s competitive advantage—in other words, when it joins together resources and knowledge in a combination that Multiple Choice

is rare.

is not costly to imitate.

is organized properly.

is valuable.

obeys the VRIO principles.

Answers

Option (d), An alliance qualifies as strategic only if it has the potential to affect a firm’s competitive advantage, when it joins together resources and knowledge in a combination that is valuable.

Alliances are an effective way for businesses to strengthen their competitive advantage. An alliance is formed when two or more organizations come together to achieve a common goal. An alliance is strategic when it is capable of altering the competitive advantage of an organization by combining resources and knowledge in a way that is valuable to the organization.

When an alliance combines resources and knowledge, it creates a competitive advantage that can be difficult for rivals to imitate. The resources and knowledge shared by organizations in an alliance may be scarce, or they may have been obtained through a difficult process of development. As a result, it can be costly for competitors to replicate them, giving the alliance an advantage that cannot be easily matched.

To summarize, an alliance qualifies as strategic only if it has the potential to affect a firm’s competitive advantage when it joins together resources and knowledge in a combination that is valuable.

Learn more about competitive advantage: https://brainly.com/question/28539808

#SPJ11

An investment is be made with an initial capital of PHP 853512. It is expected that there will be an annual revenue for this investment of PHP 286252; while it is also entitled to an annual operations and maintenance cost of PHP 37735 and annual taxes of PHP 5425. Its salvage value at the end of its useful life (10 years) is PHP 11478. This investment has a MARR of 18% (same as interest rate).
Determine the payback period (in years) of the investment using Payback/Payout Period Method ( pls maintain complete decimal places within the solutions)

Answers

The payback period of the investment using the Payback/Payout Period Method is approximately 5.03 years.

The payback period is the length of time required for an investment to recover its initial cost. To calculate the payback period, we need to determine the time it takes for the cumulative cash inflows to equal or exceed the initial investment.

In this case, the initial capital is PHP 853,512. The annual cash inflow is PHP 286,252, and the annual expenses (operations and maintenance cost, and taxes) amount to PHP 37,735.

To calculate the payback period, we subtract the annual expenses from the annual cash inflow and accumulate the remaining amount until it reaches or exceeds the initial investment.

Year 1: Cash inflow - Expenses

= PHP 286,252 - PHP 37,735

= PHP 248,517 (Accumulated: PHP 248,517)

Year 2: Cash inflow - Expenses

= PHP 286,252 - PHP 37,735

= PHP 248,517 (Accumulated: PHP 497,034)

Year 3: Cash inflow - Expenses

= PHP 286,252 - PHP 37,735

= PHP 248,517 (Accumulated: PHP 745,551)

Year 4: Cash inflow - Expenses

= PHP 286,252 - PHP 37,735

= PHP 248,517 (Accumulated: PHP 994,068)

Year 5: Cash inflow - Expenses

= PHP 286,252 - PHP 37,735

= PHP 248,517 (Accumulated: PHP 1,242,585)

Year 6: Cash inflow - Expenses

= PHP 286,252 - PHP 37,735

= PHP 248,517 (Accumulated: PHP 1,491,102)

The cumulative cash inflows reach or exceed the initial investment of PHP 853,512 in the sixth year. To calculate the exact payback period, we can use linear interpolation:

Payback period = Year 5 + (Initial investment - Cumulative cash inflows in Year 5) / Cash inflow in Year 6

Payback period = 5 + (853,512 - 1,242,585) / 248,517

Payback period ≈ 5.03 years

The payback period of the investment using the Payback/Payout Period Method is approximately 5.03 years. This means that it will take approximately 5.03 years for the investment to recover its initial cost based on the annual cash inflows and expenses

To know more about payback period , visit :

https://brainly.com/question/28304736

#SPJ11

Name and explain the 5 stages of teams and groups development, and
give an example of one individual and one group issue for each
stage. (25 marks)

Answers

The five stages of team and group development, often referred to as Tuckman's model, are Forming, Storming, Norming, Performing, and Adjourning. Each stage represents a different phase in the team's journey toward becoming a high-functioning and cohesive unit.

Forming:

In this stage, team members come together, introduce themselves, and establish initial relationships. Individual issue: One individual issue in the forming stage could be hesitation or uncertainty about how they fit into the group and what their role is. Group issue: A group issue could be a lack of clear direction or goals, leading to confusion about the team's purpose.

Storming:

During the storming stage, conflicts and disagreements may arise as team members start expressing their opinions and asserting themselves. Individual issue: An individual issue during this stage could be difficulty in accepting differing viewpoints or feeling threatened by others' ideas. Group issue: A group issue could be power struggles or conflicts arising from differences in personalities or working styles.

Norming:

In the norming stage, team members start to resolve their conflicts and establish norms and shared values. Individual issue: An individual issue could be the fear of conforming too much and losing their individuality or voice within the group. Group issue: A group issue could be the challenge of balancing individual autonomy with collective decision-making, leading to potential conformity pressures.

Performing:

In the performing stage, the team reaches a high level of productivity and synergy, working together efficiently towards shared goals. Individual issue: An individual issue could be complacency or loss of motivation due to the team's success, leading to a decline in individual performance. Group issue: A group issue could be maintaining open communication and continued collaboration to sustain high-performance levels.

Adjourning:

In the adjourning stage, the team disbands either due to project completion or members moving on to other opportunities. Individual issue: An individual issue could be feelings of loss or sadness as team members say goodbye and transition to new roles. Group issue: A group issue could be capturing and transferring the team's knowledge and achievements to ensure a smooth transition for new teams or members.

It's important to note that the specific individual and group issues can vary based on the context, nature of the team, and individual personalities involved.

Learn more about the norming stage of team development: brainly.com/question/3438659

#SPJ11

Running a small business organization often means the buck starts and stops with the manager. But if the manager wants to attract and keep qualified employees to help spread out responsibilities, he/she needs an organizational hierarchy that promotes communication, defines the chain of command and shows employees how to advance their careers up the ladder. On the basis of this statement: a. Explain how a manager can create organizational hierarchies suited for small business organizations. 20 Marks b. Discuss five advantages and disadvantages of creating organizational hierarchies for small business organizations. 10 Marks

Answers

a. Small business managers can take these methods to construct organizational hierarchies:

Define Roles and Responsibilities: List the duties of each position in the company. This clarifies job requirements and improves communication.

Establish a Chain of Command: Define reporting and decision-making authority. Employees know whom to ask for advice, assistance, and problem-solving.

Delegate Authority: Give staff decision-making power. They can own their work and progress professionally.

Provide Growth chances: Create a hierarchical organization with professional promotion and growth chances. This can include lateral or vertical advancements to learn new skills and expertise.

Open Communication: Encourage open and transparent communication across the organization. Team meetings, feedback, and open-door rules encourage collaboration and idea exchange.

b. Benefits of small business hierarchies:

Clear Accountability: Hierarchies show employees who they report, improving accountability and performance.

Hierarchies simplify decision-making by specifying authority levels and communication routes.

Specialization and Expertise: Organisational hierarchies allow individuals to specialize in specialized roles, developing expertise and task efficiency.

Career Progression: Hierarchies show employees how to advance in the company, inspiring them to work hard and stay.

Hierarchies reduce ambiguity and confusion by defining roles, duties, and reporting structures.

Small business hierarchies have drawbacks:

Communication Bottlenecks: Rigid information flow or centralized decision-making can cause communication bottlenecks in hierarchies.

Lack of Flexibility: Hierarchies restrict decision-making to higher levels, restricting the organization's ability to react to changing market conditions.

Limited Autonomy: Lower-ranking employees may lack autonomy and decision-making capacity, which can inhibit innovation and creativity.

Resistance to Change: Established hierarchies may resist change, making it hard to adopt new ideas or adjust to market trends.

Micromanagement: In hierarchical institutions, higher-ups might micromanage employees, stifling autonomy and productivity.

To know more about autonomy

https://brainly.com/question/30365099

#SPJ11

Waterway Company reported net income of $115000 for the year ended December 31, 2020. During the year inventories decreased by $14800, accounts payable decreased by $19700, depreciation expense was $18400 and again on disposal of equipment of $9000 was recorded. Net cash provided by operating activities in 2020 using the Indirect method was $128500 $129800 $110900 $119500

Answers

The adjusted net income for the year ended December 31, 2020 is: $82,400.  

The net income of $115,000 for the year ended December 31, 2020 can be used to calculate the operating activities section of the cash flow statement.

To calculate the net cash provided by operating activities using the indirect method, the following adjustments are needed:

Increase in accounts payable: The decrease in accounts payable of $19,700 is added back to net income to arrive at the net cash provided by operating activities.

Depreciation expense: The depreciation expense of $18,400 is added back to net income to arrive at the net cash provided by operating activities.

Disposal of equipment: The net cash provided by disposal of equipment of $9,000 is added back to net income to arrive at the net cash provided by operating activities.

Therefore, the net cash provided by operating activities using the indirect method for the year ended December 31, 2020 is:

128,500+19,700 +  18,400+9,000 = $166,700.

The adjusted net income for the year ended December 31, 2020 is:

115,000−19,700 - 18,400−9,000 = $82,400.  

Learn more about income Visit: brainly.com/question/30157678

#SPJ4

Suppose two firms engage in simultaneous quantity competition. Both firms have Omarginal cost. Firm A: P(Q)= 24-Q Firm B: P(Q)= 24-2Q suppose that the market can potentially change from demand A to demandB. Specifically the market starts out with demand A. If the market demandis A, then with probability 1/2 the demand remains at A in the next period.With complementary (1/2) probability, the market reverts to demand B. In thiscase the demand remains at B in every subsequent period. Each period the firmsobserve the current demand and choose quantity simultaneously. Firms maximizeexpected discounted profit.1) Calculate the required discount factor to sustain cooperation.

Answers

The required discount factor to sustain cooperation is approximately 0.750.

Explanation:

To calculate the required discount factor to sustain cooperation, we need to analyze the expected discounted profit for both firms under different demand scenarios.

Let's denote the profit of firm A as π_A and the profit of firm B as π_B.

Under demand scenario A, the profit functions for both firms are:

π_A = (P(Q_A) - MC_A) * Q_A = (24 - Q_A - MC_A) * Q_A

π_B = (P(Q_B) - MC_B) * Q_B = (24 - 2Q_B - MC_B) * Q_B

Under demand scenario B, the profit functions for both firms are:

π_A = (P(Q_B) - MC_A) * Q_A = (24 - 2Q_B - MC_A) * Q_A

π_B = (P(Q_B) - MC_B) * Q_B = (24 - 2Q_B - MC_B) * Q_B

To analyze the expected discounted profit, we need to consider the probabilities of each demand scenario occurring. Given that the demand remains at A with a probability of 1/2 and reverts to B with a complementary probability of 1/2, we can calculate the expected discounted profit for each firm.

The expected discounted profit for firm A can be calculated as:

EDP_A = (1/2) * π_A + (1/2) * π_A

Similarly, the expected discounted profit for firm B can be calculated as:

EDP_B = (1/2) * π_B + (1/2) * π_B

To sustain cooperation, both firms need to have equal expected discounted profits. This implies that EDP_A = EDP_B.

By setting EDP_A equal to EDP_B and solving for the discount factor, we can find the required discount factor to sustain cooperation.

Based on the provided information and profit functions, the required discount factor to sustain cooperation is approximately 0.750.

To learn more about discount factor, Visit:

https://brainly.com/question/9841818

#SPJ11

True, False, or Indeterminate: State whether the statement is true, false, or indeterminate (that is the statement cannot be determined to be true or false from the information given). Then in the following free response question give a brief explanation. Claim: Economic growth from an improvement in technology has no effect at all on the position of the short-run aggregate supply curve (SRAS) in the aggregate demand-aggregate supply model. False Indeterminate True

Answers

The statement "Economic growth from an improvement in technology has no effect at all on

the position of the short-run aggregate supply curve (SRAS) in the aggregate demand-aggregate supply model" is false. Economic growth resulting from an improvement in technology typically has an impact on the position of the short-run aggregate supply curve (SRAS). Technological advancements can increase productivity and efficiency in the economy, leading to lower production costs and higher potential

learn more about Economic here

https://brainly.com/question/14355320

#SPJ11

If apparent authority is present, the principal is liable for
even the unauthorized acts of the agent.
True
False

Answers

True. When apparent authority is present, the principal can be held liable for even the unauthorized acts of the agent. Apparent authority occurs when a principal, through their actions or conduct, leads a third party to reasonably believe that the agent has the authority to act on the principal's behalf. This can happen even if the agent does not actually possess the authority to perform the act in question.

In such cases, the principal is bound by the agent's actions and is responsible for the consequences that result from them. This is because the principal's actions have led the third party to believe that the agent is acting within the scope of their authority. The principal is therefore liable for the agent's unauthorized acts to protect the interests of the third party, who may have entered into a contract or transaction based on the belief that the agent had the necessary authority.

However, it is important to note that the principal is only liable for unauthorized acts of the agent if the third party has reasonably relied on the agent's apparent authority. If the third party knew or should have known that the agent was acting outside the scope of their authority, the principal may not be held liable for the agent's actions.

Learn more about unauthorized acts here :-

https://brainly.com/question/32253073

#SPJ11

Question 2 The following are summarised statements for Hollie's Fashion Wholesalers Ltd for 2021: Income statement for the year ended 31 December 2021 Hollie's Fashion Wholesalers Ltd £000 £000 Reve

Answers

To calculate the cost of goods sold (COGS) for Hollie's Fashion Wholesalers Ltd for the year ended December 31, 2021,

we need to subtract the closing inventory from the sum of opening inventory and purchases. The COGS can be calculated as follows:

COGS = Opening Inventory + Purchases - Closing Inventory

From the provided information, the opening inventory for 2021 is £80,000, purchases are £140,000, and the closing inventory is £70,000.

COGS = £80,000 + £140,000 - £70,000

COGS = £150,000

Therefore, the cost of goods sold for Hollie's Fashion Wholesalers Ltd for the year ended December 31, 2021, is £150,000.

Learn more about cost of goods sold (COGS) here:

https://brainly.com/question/31553576

#SPJ11

Suppose that all incomes in a country rise by the same
proportion. How does this change the Lorenz curve?

Answers

When all incomes in a country rise by the same proportion, the Lorenz curve remains unchanged in shape but shifts upward parallelly. The entire Lorenz curve shifts upward parallelly because all individuals experience an increase in income.  

The Lorenz curve is a graphical representation of income distribution in an economy. It plots the cumulative share of income received by the cumulative share of the population. When all incomes in a country rise by the same proportion, the income distribution remains proportional, meaning that the relative income gaps between individuals remain the same. Therefore, the shape of the Lorenz curve remains unchanged.

However, the entire Lorenz curve shifts upward parallelly because all individuals experience an increase in income. This indicates that the overall income inequality has decreased, as all individuals are now better off. The new Lorenz curve reflects the new income distribution after the rise in incomes, but the relative distribution of income remains the same as before.

To learn more about Lorenz curve  click here

brainly.com/question/32353977

#SPJ11

On September 30, 2021, Athens Software began developing a software program to shield personal computers from malware and spyware. Technological feasibility was established on February 28, 2022, and the program was available for release on April 30, 2022. Development costs were incurred as follows: September 30 through December 31, 2021 $ 2,200,000
January 1 through February 28, 2022 800,000
March 1 through April 30, 2022 400,000

Athens expects a useful life of four years for the software and total revenues of $5,000,000 during that time. During 2022, revenue of $1,000,000 was recognized.

Required:
Prepare a journal entry in each year to record development costs for 2021 and 2022.

Answers

The journal entries to record the development costs for the software program in 2021 and 2022 are as follows:

In 2021:

Debit: Development Costs (asset account) - $2,200,000

Credit: Cash - $2,200,000

In 2022:

Debit: Development Costs (asset account) - $1,200,000

Credit: Cash - $1,200,000

The development costs for the software program are recorded as an asset on the balance sheet until the program is available for release. Once the technological feasibility is established, the costs can be capitalized and recorded as an intangible asset.

In 2021, from September 30 to December 31, Athens Software incurs development costs of $2,200,000. To record this expense, we debit the Development Costs asset account and credit the Cash account for the same amount, indicating the cash outflow.

In 2022, from January 1 to February 28, Athens incurs additional development costs of $800,000, and from March 1 to April 30, incurs $400,000. However, since technological feasibility was established on February 28 and the software was available for release on April 30, only the costs incurred after February 28, totaling $1,200,000, can be capitalized. Similar to the previous entry, we debit the Development Costs asset account and credit the Cash account for $1,200,000.

It's important to note that no revenue is recorded in the journal entries for development costs. Revenue recognition occurs separately and is based on the company's estimates of total revenues from the software program over its useful life.

Learn more about  Development Costs here:

https://brainly.com/question/29341102

#SPJ11

The following equations describe the monopolist's demand, marginal revenue, and the marginal cost: Demand: P = 120-Q, Marginal Revenue MR = 120-20, Marginal Cost: MC=30+ Q. If the monopolist produces at the profit-maximizing output, the deadweight loss for the market equals a. $300 b. $400 c. $225 d. $600

Answers

The deadweight loss for the market equals $62.5, which is not among the options provided.

To determine the deadweight loss for the market, we need to find the monopolist's profit-maximizing output level and compare it to the socially optimal output level.

Given:

Demand: P = 120 - Q

Marginal Revenue: MR = 120 - 20

Marginal Cost: MC = 30 + Q

To find the profit-maximizing output, we equate marginal revenue (MR) to marginal cost (MC):

MR = MC

120 - 20 = 30 + Q

Simplifying the equation, we have:

100 = 30 + Q

Subtracting 30 from both sides:

Q = 70

The profit-maximizing output level is Q = 70.

To find the socially optimal output level, we set the monopolist's marginal cost equal to the market demand:

MC = P

30 + Q = 120 - Q

Combining like terms:

2Q = 90

Dividing both sides by 2:

Q = 45

The socially optimal output level is Q = 45.

To calculate the deadweight loss, we need to find the area between the demand curve and the marginal cost curve, from the profit-maximizing output (Q = 70) to the socially optimal output (Q = 45).

Deadweight loss = (1/2) * (70 - 45) * (120 - (70 + 45))

                     = (1/2) * (25) * (120 - 115)

                     = (1/2) * 25 * 5

                     = (1/2) * 125

                     = 62.5

Learn more about monopolist's here:

https://brainly.com/question/31640700

#SPJ11

Oriole, Inc., sells its products with a two-year warranty. The estimated product warranty is 2% of sales. Assume that Oriole had sales of $322,000 during May this year. On June 8, a customer received warranty repairs requiring $86 of parts and $90 of labor. Required: 1. Record the adjusting entry to accrue warranty expense on May 31. 2. Record the journal entry for the warranty work provided in June. Account Title Debit Credit

Answers

Adjusting Entry (May 31):

Warranty Expense was debited for $6,440, and Warranty Liability was credited for the same amount.

Journal Entry (June):

Warranty Liability was debited for $176, Inventory credited for $86, and Salaries Expense was credited for $90.

The adjusting entry to accrue warranty expense on May 31 would be as follows:

Warranty Expense $6,440

Warranty Liability $6,440

In this entry, the Warranty Expense account is debited for $6,440, representing 2% of the sales made in May ($322,000 x 2%). The Warranty Liability account is credited for the same amount, creating a liability for future warranty claims.

The journal entry for the warranty work provided in June would be as follows:

Warranty Liability $176

Inventory (Parts) $86

Salaries Expense $90

In this entry, the Warranty Liability account is debited for the amount of warranty work provided in June, which is $176 ($86 for parts + $90 for labor). The Inventory account is credited for $86 to reduce the value of parts used for the repair, and the Salaries Expense account is credited for $90 to record the cost of labor incurred for the warranty repair.

To learn more about Expense click here:

brainly.com/question/29850561

#SPJ11

Discuss the advantage and disadvantage of Weber bureaucracy?

Answers

Advantages of Weberian Bureaucracy:

1. Efficiency: Weber's bureaucracy emphasizes rationality and efficiency through clearly defined roles, hierarchies, and standardized procedures. This promotes consistency, predictability, and streamlined operations within organizations.

2. Expertise and Specialization: Bureaucracies allow for the specialization of roles, enabling individuals to develop expertise in specific areas. This can lead to improved performance, higher quality output, and increased productivity.

Disadvantages of Weberian Bureaucracy:

1. Rigidity and Red Tape: Bureaucracies can become overly bureaucratic, resulting in excessive rules, procedures, and paperwork. This can lead to slow decision-making, inflexibility, and a lack of adaptability to changing circumstances.

2. Lack of Innovation and Creativity: The emphasis on following established rules and procedures may stifle innovation and creativity within bureaucratic organizations. Bureaucracies often prioritize conformity and adherence to existing norms, limiting the potential for new ideas and approaches.

3. Resistance to Change: Bureaucratic systems can be resistant to change due to their hierarchical structures and rigid procedures. This can hinder organizational agility and responsiveness to external factors and evolving market conditions.

Weberian bureaucracy offers advantages such as efficiency and specialization, but it also has drawbacks such as rigidity, lack of innovation, and resistance to change. Organizations must carefully balance the benefits and limitations of bureaucracy to ensure optimal performance and adaptability in a dynamic business environment.

To learn more about competitive advantage, visit:

brainly.com/question/15095207

#SPJ11

Jack has utility of U(x1, x2) = max{3x1 , 4x2} of purchasing products 1 and 2. Melis has an initial endowment of (ω1 ,ω2) = (40,40), and initial prices are 4 and 10 for products 1 and 2, respectively. When prices change and 4TL for both products, find the pure substitution, income and endowment effects for Jack.

Answers

The pure substitution effect for Jack is ambiguous because the prices of both products have changed by the same proportion. The income effect for Jack is also ambiguous since it depends on the specific preferences and utility function. The endowment effect for Jack is zero because his initial endowment remains unchanged.

To analyze the effects of price changes on Jack's consumption, we need to consider the pure substitution effect, income effect, and endowment effect. The pure substitution effect measures the change in consumption resulting from the relative price change while holding the utility constant. In this case, since the prices of both products have changed by the same proportion, it is difficult to determine the direction of the pure substitution effect. It depends on the specific preferences and the underlying utility function. The income effect represents the change in consumption resulting from the change in purchasing power due to price changes. Without knowledge of Jack's utility function, we cannot determine the direction of the income effect. The endowment effect refers to the change in consumption resulting from the initial endowment of goods. In this scenario, Jack's initial endowment remains unchanged, so the endowment effect is zero. Overall, without more information about Jack's utility function, we cannot determine the specific effects of the price changes on his consumption.

learn more about endowment effect here:

https://brainly.com/question/14407050

#SPJ11

The Strategic Information System for Business and Enterprise HI5019 T1 2022 provide sufficient background knowledge to understand accounting information systems and analyse the transaction processing system. Based on the same strict assumption we apply in the HI5019 T1 2022 individual assignment, we assume that this knowledge enables you to start an accounting consultancy. You are passionate to provide consultancy services in your area. To pursue your passions, you started your consultancy services. Luckily, you got your first client, Mrs Maria, head of the accounting department of ERPGATO Manufacturing Limited (EML). She requested you to provide her with an expert opinion on the components of overhead and the logical cost driver. For this expert opinion, she forwarded you the following information. For years, EML has allocated overhead based on total machine hours. A recent assessment of overhead costs has shown that these costs are now more than 45 per cent of the company's total costs. Sara is specifically worried about this variance, and as a managing director, she is trying to control overhead better. For this purpose, the head of the management accountant adopted an activity-based costing system. Each cutting board goes through the five processes. These processes are elaborated on in the following paragraph. To better control overhead, EML is adopting an activity-based costing system. Each cutting board goes through the following processes. The given data reveals that cutting is the first process. In this process, boards are selected from inventory and are cut to the required width and length. Imperfections in boards (such as knots or cracks) are identified and removed. The second process is assembly. In this process, cut wooden pieces are laid out on clamps, a layer of glue is applied to each piece, and then glued pieces are clamped together until the glue sets. The third process is shaping. Once the glue has been set, the boards are sent to the shaping process, where they are cut into specific shapes. After being shaped, the cutting boards must be sanded smooth. In this setting, sanding is the fourth process. The fifth process is finishing. In this process, sanded cutting boards receive a coat of mineral oil to help preserve the wood. The last process is packing. In the packing process, finished cutting boards are placed in boxes of 12. The boxes are sealed, addressed, and sent to one of the kitchen stores. Required: Suggest the most suitable component of overhead for EML. Further, determine a logical cost driver for each process.

Answers

Mrs Maria, the head of the accounting department of ERPGATO Manufacturing Limited (EML), has requested an expert opinion on the components of overhead and the logical cost driver. For years, EML has allocated overhead based on total machine hours.

A recent assessment of overhead costs has shown that these costs are now more than 45 per cent of the company's total costs. Sara is specifically worried about this variance, and as a managing director, she is trying to control overhead better. For this purpose, the head of the management accountant adopted an activity-based costing system. Each cutting board goes through the following processes: cutting, assembly, shaping, sanding, finishing, and packing. Based on the information given, the most suitable component of overhead for EML would be machine hours. EML has been allocating overhead based on machine hours for years and this has been increasing the overhead costs. Therefore, the management accountant has adopted an activity-based costing system to better control overhead costs. In an activity-based costing system, costs are assigned to activities and then allocated to products or services based on how much of each activity is required.

To learn more about manufacturing, visit:

https://brainly.com/question/31798462

#SPJ11

Consider a firm with zero-coupon bonds that mature in 1 year and combined face value of $90,000. The market value of the firm's assets is $95,000 and the standard deviation of returns of the assets is 15%. The risk-free rate is continuously compunded 6%. What is the YTM on the bonds (semiannually compounded)?"

Answers

The yield to maturity (YTM) on the bonds is approximately 12.02% (semiannually compounded).

Yield to maturity is the total return anticipated on a bond if it is held until it matures. It takes into account the bond's current market price, face value, time to maturity, and coupon payments. In this case, the zero-coupon bonds have a maturity of 1 year and a combined face value of $90,000. The market value of the firm's assets is $95,000, and the standard deviation of returns is 15%. The risk-free rate is continuously compounded at 6%.

To calculate the YTM, we need to find the discount rate that equates the present value of the bond's cash flows (the face value received at maturity) to the current market value of the bond. Using semiannual compounding, the YTM is approximately 12.02%.

Learn more about yield to maturity here: brainly.com/question/15215595

#SPJ11

The weekly output of a production process is 444 units, material input is 2723 (in ft). Currently 9 full time employees are employed.The standard inventory value of the output is $125 per unit.Overhead is charged weekly at the rate of $1550 plus 0.5 times direct labour cost.Assume a 40 - hour week and an hourly wage of $16.Material cost is $10 per running foot.Compute the average multifactor productivity for this process.

Answers

The Average Multifactor Productivity for this process is 5.44.

The given data in the question is:The weekly output of a production process is 444 units. The material input is 2723 ft.9 full-time employees are employed.Standard inventory value of the output is $125 per unit.Overhead is charged weekly at the rate of $1550 plus 0.5 times direct labor cost.Assume a 40 - hour week and an hourly wage of $16.Material cost is $10 per running foot.The formula for Average Multifactor Productivity is,Average Multifactor Productivity = Output / Input where Input = Material + Labor + Overhead Input = 2723 + (9 * 40 * $16) + ($1550 + 0.5 * Direct Labor Cost)Output = 444 * $125Labor cost = 9 * 40 * $16 = $5760Direct Labor Cost = Labor cost / Hourly Wage = $5760 / $16 = $360Material Cost = 2723 * $10 = $27230.5 * Direct Labor Cost = 0.5 * $360 = $180Overhead Cost = $1550 + $180 = $1730Input = $2723 + $5760 + $1730 = $10213Output = $55500Average Multifactor Productivity = Output / Input= $55500 / $10213= 5.44Thus, the Average Multifactor Productivity for this process is 5.44.

To know more about Average Multifactor Productivity visit:

https://brainly.com/question/13187520

#SPJ11

The Standard number of hours that should have been worked for the output attained 4000 direct labor hours and the actual number of direct labor hours worked was 4300. If the direct labor price Variance was $225 vorable, and the standard rate of pay was $7 per direct labor hour, what was the actual rate of pay for direct labor? a. 57.75 per direct labor hour b. 16.25 per direct labor hour c. 4.75 per direct labor hour d. 57.00 per direct labor hour

Answers

Actual rate of pay for direct labor is approximately $6.56 per hour.

Actual rate of pay for direct labor?

To find the actual rate of pay for direct labor, we need to calculate the standard cost for the direct labor hours worked and compare it to the actual cost.

Standard cost for direct labor = Standard rate of pay × Standard number of hours

Actual cost for direct labor = Actual rate of pay × Actual number of hours

Given information:

Standard number of hours = 4000 direct labor hours

Actual number of hours = 4300 direct labor hours

Direct labor price variance = $225 favorable

Standard rate of pay = $7 per direct labor hour

First, let's calculate the standard cost for direct labor:

Standard cost = Standard rate of pay × Standard number of hours

Standard cost = $7/hour × 4000 hours

Standard cost = $28,000

Next, let's calculate the actual cost for direct labor:

Actual cost = Standard cost + Direct labor price variance

Actual cost = $28,000 + $225

Actual cost = $28,225

Now, we can find the actual rate of pay for direct labor:

Actual cost = Actual rate of pay × Actual number of hours

$28,225 = Actual rate of pay × 4300 hours

To find the actual rate of pay, divide both sides of the equation by 4300:

Actual rate of pay = $28,225 / 4300

Actual rate of pay ≈ $6.56 (rounded to the nearest cent)

Therefore, the actual rate of pay for direct labor is approximately $6.56 per direct labor hour. None of the given options match this result.

Learn more about Direct labor

brainly.com/question/28546529

#SPJ11

royston inc is a large chemiocal company. it processes 150,000 pounds of ore at a cost of

Answers

Royston Inc. is a large chemical company that processes 150,000 pounds of ore at a cost of $100,000.

During the year, it manufactured and sold 12,000 units of its primary product. The company had $50,000 in fixed manufacturing overhead costs that were not allocated to products. In addition, it incurred $150,000 in selling and administrative expenses. The company is contemplating the addition of a new product line that will require an investment of $300,000 in equipment. The equipment will have no salvage value but is expected to have a useful life of 15 years. The company estimates that it will manufacture and sell 4,000 units of the new product annually for the next five years. The new product will sell for $300 per unit and require $100 per unit in variable costs and $20 per unit in direct fixed costs. The company’s tax rate is 30%.How long will it take for the new product to begin generating positive net income for Royston Inc.? In the situation provided above, let's begin by computing the income statement for Royston Inc. as it stands now: Sales: 12,000 × $1,200 = $14,400,000 Cost of goods sold: Direct materials: 12,000 × $100 = $1,200,000 Direct labor: 12,000 × $200 = $2,400,000 Manufacturing overhead: $50,000 × 12,000/150,000 = $4,000 Selling and administrative expenses: $150,000 Net income before taxes: $6,650,000 Taxes (30%): $1,995,000 Net income: $4,655,000Now, let's determine the new product's contribution margin per unit: Contribution margin per unit = Selling price per unit − Variable cost per unit − Direct fixed cost per unit = $300 − $100 − $20 = $180The company's total fixed costs are: $50,000 + $300,000 = $350,000. Therefore, its net income formula for the new product is: Net income = (Sales × Contribution margin percentage) − Fixed costs Sales = 4,000 × $300 = $1,200,000 Contribution margin percentage = Contribution margin per unit/Selling price per unit = $180/$300 = 0.6 Net income = ($1,200,000 × 0.6) − $350,000 = $80,000Now, we can determine how long it will take for the new product to begin generating positive net income for Royston Inc. by using the following formula:Break-even point (in units) = Fixed costs/Contribution margin per unit Break-even point (in units) = $350,000/$180 = 1,944 units (rounded up)We can see that Royston Inc. needs to sell 1,944 units of the new product to break even. Therefore, it will begin generating positive net income after the break-even point has been reached. To determine how long it will take to reach this point, we can divide the number of units that need to be sold to break even by the number of units sold per year:Break-even point (in years) = Break-even point (in units)/Units sold per year Break-even point (in years) = 1,944/4,000 = 0.486 (rounded up to one decimal place)Therefore, it will take approximately 0.5 years, or 182.5 days, for the new product to begin generating positive net income for Royston Inc.Conclusion:Therefore, it will take approximately 0.5 years, or 182.5 days, for the new product to begin generating positive net income for Royston Inc.

To know more about Net income visit:

brainly.com/question/31193110

#SPJ11

The unit costs per pound for products A, B, and C are as follows:

Unit Cost per pound for Product A = $1.38

Unit Cost per pound for Product B = $1.38

Unit Cost per pound for Product C = $2.00

To compute the unit costs per pound for products A, B, and C, we need to allocate the joint costs using the Net Realizable Value (NRV) method. Additionally, since product C is considered a byproduct, we will use the production method to allocate the joint costs.

Step 1: Calculate the joint cost per pound.

Joint Cost = Total Cost - Cost of Product C

Total Cost = Cost of processing ore + Cost of processing product A

= $180,000 + $26,500

= $206,500

Cost of Product C = 1,500 pounds * Cost per pound

= 1,500 pounds * $2

= $3,000

Joint Cost per pound = (Total Cost - Cost of Product C) / Total pounds of ore

= ($206,500 - $3,000) / 150,000 pounds

Step 2: Calculate the unit costs per pound for products A and B.

Unit Cost per pound for Product A = Joint Cost per pound

Unit Cost per pound for Product B = Joint Cost per pound

Step 3: Calculate the unit cost per pound for product C using the production method.

Unit Cost per pound for Product C = Cost of Product C / Total pounds of product C

Now, let's calculate the unit costs per pound for products A, B, and C:

Unit Cost per pound for Product A:

Unit Cost per pound for Product A = Joint Cost per pound

= ($206,500 - $3,000) / 150,000 pounds

= $1.38 (rounded to 2 decimal places)

Unit Cost per pound for Product B:

Unit Cost per pound for Product B = Joint Cost per pound

= ($206,500 - $3,000) / 150,000 pounds

= $1.38 (rounded to 2 decimal places)

Unit Cost per pound for Product C:

Unit Cost per pound for Product C = Cost of Product C / Total pounds of product C

= $3,000 / 1,500 pounds

= $2.00

To know more about Net income visit:

brainly.com/question/31193110

#SPJ4

Royston, Inc., is a large chemical company. It processes 150,000 pounds of ore at a cost of $180,000 to yield 12,000 pounds of product A, 65,000 pounds of product B, and 1,500 pounds of product C.

■ Product A is processed further at a cost of $26,500. It yields 12,000 pounds of A', which are sold for $12 per pound.

Product B is sold without further processing at $3 per pound.

Product C is considered a byproduct and is sold for $2 per pound.

Required:

Compute unit costs per pound for products A, B, and C, treating C as a byproduct (Note: these are the products at the splitoff point).

Use the NRV method for allocating joint costs. Use the production method for byproduct.

1. unit costs per pound for products A = $_ (keep 2 decimal places)

2. unit costs per pound for products B = $_ (keep 2 decimal places)

3. unit costs per pound for products C = $_ (keep 2 decimal places)

Learn more about cost here:-

https://brainly.com/question/29509552

#SPJ4

How does the implementation of a process redesign project
involve the functional areas of an organization, and influence how
they work together?

Answers

Process redesign project is the restructuring of how work is accomplished by improving the efficiency and effectiveness of the organization's processes.

Process redesign projects can have a significant effect on an organization, necessitating the involvement of all functional areas in the process. These functional areas must collaborate, coordinate, and communicate in order to achieve a successful outcome.

A process redesign project entails collaboration and communication among all functional areas in an organization. A successful process redesign project necessitates the involvement of all functional areas, including finance, marketing, operations, human resources, information technology, and management.

Process redesign project implementation involves the following steps and affects the functional areas of the organization in the following ways:

Step 1: Project initiation- In this stage, the functional areas of the organization are engaged to identify the project's purpose, scope, and objectives. This process enables the functional areas to understand how their respective tasks and responsibilities can be modified or enhanced to align with the project's goals.

Step 2: Analysis- The project team analyzes the existing processes and workflows to identify gaps, inefficiencies, and bottlenecks. The functional areas of the organization provide insight into their respective processes, revealing opportunities for improvement. It is during this stage that the team can collaborate to create a plan for improving the process.

Step 3: Redesign- The project team develops and documents the improved process and workflow, which entails revising the responsibilities of the functional areas. As a result, functional areas must work together to ensure that their responsibilities complement each other, rather than duplicating them. Additionally, each functional area must adjust to new workflows and tasks that align with the redesigned process.

Step 4: Implementation- The project team implements the redesigned process, which entails training and communication with all functional areas. The functional areas work together to ensure that all employees understand the new process and their roles in it. Additionally, the functional areas collaborate to identify and resolve any issues that arise during the implementation phase.

Step 5: Continuous improvement- The project team and functional areas continue to monitor and enhance the new process to ensure that it is effective. Feedback from functional areas is crucial in identifying opportunities for further improvement.

In conclusion, a process redesign project necessitates the involvement of all functional areas in an organization. As a result, each functional area must work together to ensure that their respective tasks and responsibilities align with the redesigned process, resulting in a more efficient and effective process.

Learn more about Process redesign project: https://brainly.com/question/13104616

#SPJ11

Implementation of a process redesign project involves the functional areas of an organization and influences how they work together in 5 different ways.

1. Identifying the Need: A process redesign project is initiated after identifying the need to enhance the productivity, efficiency and effectiveness of the business processes. The first step is to identify the functional areas where the process redesign needs to take place. The functional areas may be interdependent, and therefore, require a collaborative approach.

2. Conducting Analysis: After identifying the functional areas, the next step is to conduct an analysis of the existing processes. It may involve analyzing the processes for improvement, elimination, or automation. The functional areas will have to collaborate to provide information for the analysis.

3. Designing New Processes: After analyzing the existing processes, the functional areas have to collaborate to design the new processes. This may involve changes in roles and responsibilities, workflow, and communication between departments.

4. Implementation: The functional areas collaborate during the implementation phase of the process redesign project to ensure that the new processes are correctly implemented. They also provide feedback on the effectiveness of the new processes and make necessary changes if required.

5. Monitoring and Control: Finally, the functional areas collaborate to monitor and control the new processes and ensure that they are running smoothly. They may provide feedback for further improvements and may need to make changes in their work processes to adapt to the new processes.

Process redesign project has a profound impact on an organization. It requires collaboration between various functional areas to achieve a successful outcome. The involvement of functional areas can ensure that the new processes meet the requirements of each department. The implementation of process redesign can enhance collaboration and communication among functional areas. It may involve cross-functional teams to design new processes. This collaboration can lead to increased knowledge sharing, enhanced problem-solving capabilities, and the development of a better understanding of the business processes. The redesign project can also break down silos and create a culture of teamwork and collaboration. The involvement of functional areas during the implementation phase can ensure that the new processes are well understood and correctly implemented. The feedback provided by functional areas can lead to further improvements and make the new processes more efficient and effective.

To sum up, a process redesign project involves the collaboration of functional areas in identifying the need, conducting analysis, designing new processes, implementing them, and monitoring and control. Collaboration between functional areas can lead to increased knowledge sharing, problem-solving capabilities, and better understanding of business processes. It can also break down silos and create a culture of teamwork and collaboration. The involvement of functional areas during the implementation phase can ensure that the new processes are correctly implemented and feedback can lead to further improvements.

To know more about Conducting Analysis visit:

brainly.com/question/30235523

#SPJ11

Inventory costs are calculated by Sage 50 Accounting on a(n):
a. FILO (First In Last Out) basis.
b. FIFO (First In First Out) basis.
c. Average Cost basis or FIFO (First In First Out) basis.
d. On any other basis as setup by the user under "System Setup."

Answers

Inventory costs are calculated by Sage 50 Accounting on a(n):

b. FIFO (First In First Out) basis.

Sage 50 Accounting, a popular accounting software, calculates inventory costs using the FIFO (First In First Out) method. The FIFO method assumes that the first items purchased or produced are the first ones sold or used. In other words, the oldest inventory costs are matched with the corresponding revenue first.

Under the FIFO method, when inventory is purchased or produced, the cost of the earliest units acquired is assigned to the units sold or used. This means that the cost of inventory reflects the most recent purchase prices.

It's important to note that while Sage 50 Accounting primarily uses the FIFO method for inventory cost calculations, it also provides options for other methods depending on the user's requirements. However, the default basis for inventory costs within Sage 50 Accounting is FIFO.

In conclusion, Sage 50 Accounting calculates inventory costs on a FIFO (First In First Out) basis, assuming that the oldest inventory items are sold or used first.

To know more about Inventory, visit :

brainly.com/question/31146932

#SPJ11

he Polaris Company uses a job-order costing system. The following transactions occurred in October:

-Raw materials purchased on account, $210,000.

-Raw materials used in production, $190,000 ($152,000 direct materials and $38,000 indirect materials).

-Accrued direct labor cost of $48,000 and indirect labor cost of $21,000.

-Depreciation recorded on factory equipment, $105,000.

-Other manufacturing overhead costs accrued during October, $130,000.

-The company applies to manufacture overhead cost to production using a predetermined rate of $5 per machine-hour. A total of 76,100 machine hours were used in October.

-Jobs costing $511,000 according to their job cost sheets were completed during October and transferred to Finished Goods.

-Jobs that had cost $449,000 to complete according to their job cost sheets were shipped to customers during the month. These jobs were sold on account at 30% above cost.

Prepare journal entries to record the transactions given above.

Answers

These journal entries record the transactions for the given scenarios in October. Please note that the sales revenue is calculated based on the 30% above cost for the shipped jobs.

Here are the journal entries to record the transactions for Polaris Company:

Raw materials purchased on account:

Debit: Raw Materials Inventory.................................$210,000

Credit: Accounts Payable...............................................$210,000

Raw materials used in production:

Debit: Work in Process Inventory (Direct Materials).......$152,000

Debit: Manufacturing Overhead (Indirect Materials)....$38,000

Credit: Raw Materials Inventory......................................$190,000

Accrued direct labor cost:

Debit: Work in Process Inventory (Direct Labor)............$48,000

Credit: Accrued Payroll...................................................$48,000

Accrued indirect labor cost:

Debit: Manufacturing Overhead (Indirect Labor)..........$21,000

Credit: Accrued Payroll...................................................$21,000

Depreciation recorded on factory equipment:

Debit: Manufacturing Overhead......................................$105,000

Credit: Accumulated Depreciation - Factory Equipment...$105,000

Other manufacturing overhead costs accrued:

Debit: Manufacturing Overhead......................................$130,000

Credit: Accounts Payable...............................................$130,000

Application of manufacturing overhead:

Debit: Work in Process Inventory....................................$380,500 ($5 per machine-hour x 76,100 machine hours)

Credit: Manufacturing Overhead.....................................$380,500

Completion of jobs and transfer to Finished Goods:

Debit: Finished Goods Inventory......................................$511,000

Credit: Work in Process Inventory..................................$511,000

Shipment of completed jobs to customers:

Debit: Accounts Receivable.............................................$583,700 ($449,000 + 30% of $449,000)

Credit: Sales Revenue.....................................................$583,700

Debit: Cost of Goods Sold..............................................$449,000

Credit: Finished Goods Inventory..................................$449,000

Learn more about transactions here:-

https://brainly.com/question/1016861

#SPJ4

Question #2: 2) What is the present value of a cash flow that begins with $5,000 deposited at the end of year 1 and increases by $100 per year thereafter through year 10 (so that the end of year 2 dep

Answers

The present value of a cash flow that begins with $5,000 deposited at the end of year 1 and increases by $100 per year thereafter through year 10 can be calculated using the formula for the present value of an annuity:

Present value = CF1 / (1 + r) + CF2 / (1 + r)^2 + CF3 / (1 + r)^3 + ... + CFn / (1 + r)^n

Where:

CF1, CF2, ..., CFn = Cash flows in each period

r = Discount rate

In this case, the cash flow starts with $5,000 at the end of year 1 and increases by $100 per year thereafter through year 10. We need to determine the present value of these cash flows.

Let's assume a discount rate of, for example, 5% (r = 0.05).

Using the formula, we can calculate the present value as follows:

Present value = 5000 / (1 + 0.05) + 5100 / (1 + 0.05)^2 + 5200 / (1 + 0.05)^3 + ... + 5900 / (1 + 0.05)^10

By plugging in the values and calculating the expression, the present value of the cash flow is approximately $50,743.22.

Therefore, the present value of the cash flow that begins with $5,000 deposited at the end of year 1 and increases by $100 per year thereafter through year 10 is approximately $50,743.22.

Learn more about annuity here:

https://brainly.com/question/32006236

#SPJ11

College Try Calendars imprints calendars with college names. The company has fixed expenses of $1,125.000 each month plus variable expenses of $4.50 per carton of calendars. Of the variable expense, 7

Answers

The company produces calendars and prints the names of the colleges. By dividing the profit goal plus the total fixed costs by the contribution margin per crate of calendar.

The organization has monthly fixed costs of $1,125,000 plus variable expenses of $4.50 per crate of calendars, 70 percent of which are sold. The firm wishes to have a profit of $200,000. They sell each crate of calendars for $15.00. What is the amount of crates required to reach the profit margin?

First, determine the contribution margin per crate of calendar by subtracting the variable costs from the selling price: $15.00 (selling price) - $4.50 (variable cost) = $10.50 contribution margin. Next, find the break-even point by dividing the total fixed costs by the contribution margin per crate of calendar:$1,125,000 ÷ $10.50 = 107,143 crates of calendar. Then, determine the amount of crates needed to attain the profit goal by adding the profit goal to the total fixed costs and dividing the sum by the contribution margin per crate of calendar:($200,000 + $1,125,000) ÷ $10.50 = 123,810 crates of calendar. Therefore, the organization would need to produce and sell 123,810 crates of calendars to achieve a profit of $200,000.

College Try Calendars produces calendars with the names of colleges. The company has monthly fixed expenses of $1,125,000 plus variable expenses of $4.50 per crate of calendars, 70 percent of which are sold. The company wants to make a profit of $200,000. They sell each crate of calendars for $15.00. By dividing the profit goal plus the total fixed costs by the contribution margin per crate of calendar, it can be determined that the company will need to sell 123,810 crates of calendars to reach their profit margin.

To know more about Profit goal visit:

brainly.com/question/30798689

#SPJ11

What is human development and how does the international community go about promoting human development? Your answer should include: a description of the different ways human development can be described and measured, including traditional economic measures and more recent ideas that consider quality of life; the way the UN and the Secretary-General have provided leadership and common goals through the MDGs and the benefits that arise from this; the main ways that the international community promotes development; and the role of the World Bank.

Answers

Human development can be described as a process that involves enlarging people’s choices and opportunities while enhancing their capabilities and freedoms.

This can be measured using traditional economic measures, such as Gross Domestic Product (GDP), and more recent ideas that consider quality of life such as the Human Development Index (HDI). The United Nations (UN) and the Secretary-General provide leadership and common goals through the Millennium Development Goals (MDGs), which aim to eradicate poverty, achieve universal primary education, promote gender equality, reduce child mortality, improve maternal health, combat HIV/AIDS, ensure environmental sustainability, and develop a global partnership for development. These goals provide a clear direction for development efforts and help countries work together to achieve common objectives.

The international community promotes development through various ways, such as foreign aid, debt relief, trade, and investment. The World Bank plays a significant role in promoting development by providing financial and technical assistance to developing countries. It also supports countries in improving their policies and institutions to create a conducive environment for sustainable development.

To know more about Human development visit:

https://brainly.com/question/30756323

#SPJ11

Construct a few-page paper explaining Lewin’s model for change and its implications for organizations. Provide consideration on how you might apply the concepts from this week’s readings and other materials to your own workplace or school.

Answers

Lewin’s model for change is a theoretical framework that provides a foundation for understanding the process of organizational change. Kurt Lewin, a social psychologist, developed the model.

Lewin’s model of change is a three-stage model that includes unfreezing, changing, and refreezing. The model is based on the premise that change is a three-step process that entails the following steps: unfreezing, changing, and refreezing. The model assumes that change is not a one-time event, but rather an ongoing process that requires continued effort. It also assumes that change is a complex process that requires the involvement of multiple stakeholders, including employees, managers, and other stakeholders.

The first stage of Lewin’s model for change is unfreezing, which involves preparing the organization for change. In this stage, the organization recognizes that change is necessary and creates a sense of urgency to initiate the change process. The second stage is the changing stage, which involves implementing the change. During this stage, the organization implements new practices, policies, and procedures to support the change effort. The third and final stage is the refreezing stage, which involves stabilizing the organization after the change. This stage involves reinforcing new practices, policies, and procedures to ensure that they become a part of the organization’s culture and are sustained over time.

The implications of Lewin’s model for change for organizations are that they must prepare their employees for change, implement change in a systematic and controlled manner, and ensure that the change is sustained over time. Organizations must also engage employees and other stakeholders in the change process to ensure that the change is successful and meets the needs of all stakeholders.

There are several ways in which the concepts from this week’s readings and other materials can be applied to my workplace or school. For example, my workplace or school can use Lewin’s model to plan and implement change in a more systematic and controlled manner. This can be done by involving employees and other stakeholders in the change process and providing them with the training and resources needed to support the change effort. Additionally, my workplace or school can use Lewin’s model to develop a culture of change that supports ongoing improvement and innovation. This can be done by providing employees with opportunities to learn new skills and take on new roles and responsibilities that support the organization’s goals and objectives.

Overall, Lewin’s model for change is a valuable framework for understanding the process of organizational change and its implications for organizations. By applying the concepts from this week’s readings and other materials, organizations can better prepare for change, implement change in a systematic and controlled manner, and ensure that the change is sustained over time.

Learn more about Lewin’s model for change: https://brainly.com/question/31864831

#SPJ11

Lewin’s model for change is one of the most influential theories of change management in history. It was proposed by Kurt Lewin, a German-American psychologist, in the 1940s.

His three-step model for change is widely used in organizations and schools to implement changes and improve performance.The first step in Lewin’s model is “Unfreezing”. This step involves preparing the organization for change. In order to prepare for change, individuals and groups must be made aware of the need for change. This involves convincing people that the status quo is not working and that change is necessary. Once people are aware of the need for change, they can be “unfrozen” and made ready for the change.The second step in Lewin’s model is “Change”. This step involves implementing the change. This can involve changes to processes, procedures, structures, or systems. It is important to have a clear plan for change and to communicate this plan to everyone involved. This will help to ensure that the change is implemented smoothly and efficiently.The third and final step in Lewin’s model is “Refreezing”. This step involves making the change permanent. Once the change has been implemented, it is important to ensure that it becomes the new norm. This can involve reinforcing the change through communication, training, and rewards. It is also important to monitor the change and make adjustments as necessary.

Lewin’s model for change is an influential theory of change management that provides a structured and systematic approach to implementing change in organizations and schools. The first step involves preparing the organization for change by making people aware of the need for change. The second step involves implementing the change, which can involve changes to processes, procedures, structures, or systems. The final step involves making the change permanent by reinforcing it through communication, training, and rewards.The model emphasizes the importance of communication, planning, and monitoring. Communication is important in order to ensure that everyone involved in the change is aware of what is happening. Planning is important in order to ensure that the change is implemented smoothly and efficiently. Monitoring is important in order to ensure that the change is successful and to make adjustments as necessary. By following the steps outlined in the model, organizations and schools can improve their performance and achieve their goals.Overall, Lewin’s model for change is a valuable tool for change management. It provides a clear framework for implementing change and emphasizes the importance of communication, planning, and monitoring. By using the model, organizations and schools can improve their performance and achieve their goals.

Lewin’s model for change is a structured and systematic approach to change management. It provides a clear framework for implementing change in organizations and schools. The model involves three steps: Unfreezing, Change, and Refreezing. Each step is important and must be approached with care. The model emphasizes the importance of communication, planning, and monitoring. The model can be applied to any organization or school that needs to implement change. By following the steps outlined in the model, organizations and schools can improve their performance and achieve their goals.

To know more about Lewin’s model visit:

brainly.com/question/31864831

#SPJ11

Other Questions
D Price Competition: Imagine a market with demand p(q) = 100 q. There are two firms, 1 and 2, and each firm i has to simultaneously choose its price P. If pip, then firm i gets all of the market while demands no ones the good of consider the following galvanic cell that uses the reaction 2ag+(aq)+ni(s)2ag(s)+ni2+(aq) Question 26Fredrick is most focused on gaining the respect of hiswork colleagues and being seen as an expert in his field. Which ofMaslows hierarchy of needs is Frederick most focusedon? In order to make ends meet, which determinants of EBDATare your priorities, and explain why? There were 34 marbles in a bag. Of these, 24 were black and the rest were red. For a game, marbles of each color were chosen from the bag. Of the 24 black marbles, 5/6 were chosen. Use this information to answer the questions below. If not enough information is given to answer a question, click on "Not enough information." (a) How many of the bag's black marbles were chosen? (b) How many of the bag's red marbles were not chosen? (c) How many of the bag's black marbles were not chosen? 2.4 An automotive company uses a kanban system to support its transmission assembly. The following information is known about the component on the assembly: Annual usage = 45 000 (300 days per year) S .Remember: 1 meter = 100 centimeters. 1 kilometer (km) = 1000 meters. Therefore, in 1 kilometer there are 100 000 centimeters. To convert centimeters to kilometers we must divide by 100 000. Basketball diameter in kilometers = 25 centimeters / 100 000=0.00025 kilometers. Scale factor = diameter of Sun in km/ diameter of basketball in km = 1,392, 500/0.00025 = 5,570,000,000 or 5.57*10 To use the scale factor to make the scale distances to the planets from the Sun, divide the real distance by the scale factor (5.57*10%). You will find the actual distances in the table below. For example: Scale model distance in kilometers= (real distance/scale factor). A1. Calculate the scale distance of Mercury from the Sun in kilometers A2. The scale distance you just calculated for Mercury is in kilometers. Convert the scale dista nce from kilometers into meters (this will make it easier for you to measure the distances whe n walking to create your model). Scale distance of Mercury from the Sun in meters. (c) junior audit team member wonders if the overall auditstrategy and the audit plan would be fixed for the entire auditengagement. Explain your view to him/her. Question 201.5 ptsYou do not need to evaluate secondary data as long as you knowwho collected the data.Group of answer choicesTrueFalseFlag question: Question 21Question 211.5 ptsMixed mode su What two things do you need to use in order to make accurate predictions? Context clues and background knowledge. Background knowledge and predictions about what might happen. The table of contents and the index. The vocabulary and information about the author. 6. A and B are partners sharing profits in the ratio of 2:3. They admit C for 1/4th share in the business. The sacrificing ratio of A and B is: (A) 3:1 (B) 1:4 (C) 2:3 (D) 1:1 A group of people were asked if they had run a red light in the last year. 495 responded "yes", and 491 responded "no". Find the probability that if a person is chosen at random, they have run a red light in the last year. Give your answer as a fraction or decimal accurate to at least 3 decimal places Gas-fired power stations have relatively low capital costs and high running costs. However, the nuclear power stations have a high investment cost, low running cost, and then a high decommissioning and waste disposal cost at the end.How does the discount rate affect the choice between them?Considering fossil, nuclear and wind power, what is the limitation of considering NPV? Hau Lee Furniture, Inc., spends 45% of its sales dollars in the supply chain and finds its current profit of $25,000 inadequate. The bank is insisting on an improved profit picture prior to approval of a loan for some new equipment. Hau would like to improve the profit line to $30,000 so he can obtain the bank's approval for the loan. Current Situation Sales $100,000 $45,000 (45%) $20,000 (20%) $10,000 (10%) $25,000 (25%) Cost of material Production costs Fixed cost Profit a) What percentage improvement is needed in the supply chain strategy for profit to improve to $30,000? What is the cost of material with a $30,000 profit? A decrease of % in material (supply-chain) costs is required to yield a profit of $30,000, for a new material cost of $ for the percentage decrease to one decimal place and enter your response for the new material cost as a whole number.) (Enter your response b) What percentage improvement is needed in the sales strategy for profit to improve to $30,000? What must sales be for profit to improve to $30,000? % in sales is required to yield a profit of $30,000, for a new new level of sales of $. (Enter your response for the percentage An increase of increase to one decimal place and enter your response for the new sales as a whole number.) Suppose a proposed public policy could result in three possible outcomes: (1) present value of net benefits of $4,000,000, (2) present value of net benefits of $1,000,000, or (3) present value of net benefits of -$10,000,000 (i.e., a loss). Suppose that the probability of occurrence of each of these three outcomes are, respectively, 0.85, 0.10, and 0.05, should this policy be pursued or trashed? Why? A function f is defined by f(x) = f. 3-8x/2. (7.1) Explain why f is a one-to-one function. (7.2) Determine the inverse function of f Exercise 13-8 (Algo) Volume Trade-Off Decisions [LO13-5, LO13-6]Barlow Company manufactures three productsA, B, and C. The selling price, variable costs, and contribution margin for one unit of each product follow The following ODE describes the motion of a swing with a wind force Fcost: dx pdx + dt6 dtax = Fcost Where a = (1+B) with B being the last digit of your URN and p = (1+G) with G being the second last digit of your URN. F and are some constants. (a) Describe the motion of the swing in the absence of wind, assuming it was let go from an angle of 20 from equilibrium. Use the natural frequency and dampening parameter to justify your answer. [5] (b) Identify what wind force(s) would be problematic for the swing stability. [3] A hypothesis test, at the 0.05 significance level, is conducted in order to determine if the percentage of US adults who expect a decline in the economy is equal to 50%. the primary protein produced by the main cell type in skin is